Lyvia By Palace construction progress

The registered completion date for Lyvia By Palace in Dubai Creek Harbour is July 2029. At the last site inspection, in March 2026, it was 4.8% built. The developer is Dubai Creek Harbour.

4.8%

Built, at the site inspection of 17 March 2026

Running behind its date

Registered completion date
July 2029
Finish at recent pace
December 2035
Construction started
November 2025
First registered
September 2025
Units
481
Escrow bank
Emirates Islamic Bank
Name in Arabic
ليفيا باي بالاس
Project number
4098
Site inspections
2

Schedule

Between September 2025 and March 2026 the site added about 0.8 points a month. At that rate it would finish around December 2035, more than three months after its registered date of July 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 March 2026

4.8%+4.8 pts

  • Lyvia By Palace construction site, inspection photo 1, 17 March 2026
  • Lyvia By Palace construction site, inspection photo 2, 17 March 2026
  • Lyvia By Palace construction site, inspection photo 3, 17 March 2026
  • Lyvia By Palace construction site, inspection photo 4, 17 March 2026

19 September 2025

0%

  • Lyvia By Palace construction site, inspection photo 1, 19 September 2025
  • Lyvia By Palace construction site, inspection photo 2, 19 September 2025

All 6 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Lyvia By Palace?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lyvia By Palace handover date?
The registered completion date is July 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lyvia By Palace?
Lyvia By Palace was 4.8% built at the site inspection on 17 March 2026. The site has been inspected 2 times since September 2025. The Land Department took 6 site photos at its inspections.
Is Lyvia By Palace delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Lyvia By Palace?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Lyvia By Palace?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.