Island Park II construction progress

The register lists Island Park II in Dubai Creek Harbour as complete, with a registered completion date of February 2025. Its last site inspection on record was in February 2025. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 18 February 2025

Construction complete

Registered completion date
February 2025
Construction started
August 2017
First registered
August 2017
Units
160
Escrow bank
Dubai Islamic Bank
Name in Arabic
Ii آيلاند بارك
Project number
1896
Site inspections
7

Schedule

The register lists Island Park II as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 February 2025

100%+41 pts

  • Island Park II construction site, inspection photo 1, 18 February 2025
  • Island Park II construction site, inspection photo 2, 18 February 2025
  • Island Park II construction site, inspection photo 3, 18 February 2025
  • Island Park II construction site, inspection photo 4, 18 February 2025

13 September 2024

59%+18 pts

  • Island Park II construction site, inspection photo 1, 13 September 2024
  • Island Park II construction site, inspection photo 2, 13 September 2024
  • Island Park II construction site, inspection photo 3, 13 September 2024
  • Island Park II construction site, inspection photo 4, 13 September 2024

24 April 2024

40%+34 pts

  • Island Park II construction site, inspection photo 1, 24 April 2024
  • Island Park II construction site, inspection photo 2, 24 April 2024
  • Island Park II construction site, inspection photo 3, 24 April 2024
  • Island Park II construction site, inspection photo 4, 24 April 2024

20 September 2023

6.5%+3.5 pts

  • Island Park II construction site, inspection photo 1, 20 September 2023
  • Island Park II construction site, inspection photo 2, 20 September 2023
  • Island Park II construction site, inspection photo 3, 20 September 2023
  • Island Park II construction site, inspection photo 4, 20 September 2023

4 June 2020

3.0%

  • Island Park II construction site, inspection photo 1, 4 June 2020
  • Island Park II construction site, inspection photo 2, 4 June 2020
  • Island Park II construction site, inspection photo 3, 4 June 2020
  • Island Park II construction site, inspection photo 4, 4 June 2020

12 June 2018

3.0%+2.9 pts

  • Island Park II construction site, inspection photo 1, 12 June 2018
  • Island Park II construction site, inspection photo 2, 12 June 2018
  • Island Park II construction site, inspection photo 3, 12 June 2018

28 February 2018

0.1%

  • Island Park II construction site, inspection photo 1, 28 February 2018
  • Island Park II construction site, inspection photo 2, 28 February 2018
  • Island Park II construction site, inspection photo 3, 28 February 2018

All 36 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Island Park II?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Island Park II handover date?
Construction of Island Park II is recorded as complete, with a registered completion date of February 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Island Park II?
Island Park II was 100% built at the site inspection on 18 February 2025. The site has been inspected 7 times since February 2018. The Land Department took 36 site photos at its inspections.
Is Island Park II delayed?
The register lists construction as complete.
Who is building Island Park II?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Island Park II?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.