Harbour Views construction progress

The register lists Harbour Views in Dubai Creek Harbour as complete, with a registered completion date of November 2020. Its last site inspection on record was in November 2020. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 5 November 2020

Construction complete

Registered completion date
November 2020
Construction started
June 2016
First registered
January 2016
Units
784
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
هاربور فيوز
Project number
1710
Site inspections
11

Schedule

The register lists Harbour Views as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2020

100%+5.0 pts

  • Harbour Views construction site, inspection photo 1, 5 November 2020
  • Harbour Views construction site, inspection photo 2, 5 November 2020
  • Harbour Views construction site, inspection photo 3, 5 November 2020
  • Harbour Views construction site, inspection photo 4, 5 November 2020

4 June 2020

95%+4.8 pts

  • Harbour Views construction site, inspection photo 1, 4 June 2020
  • Harbour Views construction site, inspection photo 2, 4 June 2020
  • Harbour Views construction site, inspection photo 3, 4 June 2020
  • Harbour Views construction site, inspection photo 4, 4 June 2020

28 January 2020

90%+6.7 pts

  • Harbour Views construction site, inspection photo 1, 28 January 2020
  • Harbour Views construction site, inspection photo 2, 28 January 2020
  • Harbour Views construction site, inspection photo 3, 28 January 2020
  • Harbour Views construction site, inspection photo 4, 28 January 2020

7 October 2019

84%+7.5 pts

  • Harbour Views construction site, inspection photo 1, 7 October 2019
  • Harbour Views construction site, inspection photo 2, 7 October 2019
  • Harbour Views construction site, inspection photo 3, 7 October 2019
  • Harbour Views construction site, inspection photo 4, 7 October 2019

1 July 2019

76%+15 pts

  • Harbour Views construction site, inspection photo 1, 1 July 2019
  • Harbour Views construction site, inspection photo 2, 1 July 2019
  • Harbour Views construction site, inspection photo 3, 1 July 2019
  • Harbour Views construction site, inspection photo 4, 1 July 2019

26 February 2019

61%+20 pts

  • Harbour Views construction site, inspection photo 1, 26 February 2019
  • Harbour Views construction site, inspection photo 2, 26 February 2019
  • Harbour Views construction site, inspection photo 3, 26 February 2019
  • Harbour Views construction site, inspection photo 4, 26 February 2019

5 September 2018

41%+8.8 pts

  • Harbour Views construction site, inspection photo 1, 5 September 2018
  • Harbour Views construction site, inspection photo 2, 5 September 2018
  • Harbour Views construction site, inspection photo 3, 5 September 2018
  • Harbour Views construction site, inspection photo 4, 5 September 2018

10 May 2018

32%+8.0 pts

  • Harbour Views construction site, inspection photo 1, 10 May 2018
  • Harbour Views construction site, inspection photo 2, 10 May 2018
  • Harbour Views construction site, inspection photo 3, 10 May 2018
  • Harbour Views construction site, inspection photo 4, 10 May 2018

16 January 2018

24%+7.8 pts

  • Harbour Views construction site, inspection photo 1, 16 January 2018
  • Harbour Views construction site, inspection photo 2, 16 January 2018
  • Harbour Views construction site, inspection photo 3, 16 January 2018
  • Harbour Views construction site, inspection photo 4, 16 January 2018

18 September 2017

16%+12 pts

  • Harbour Views construction site, inspection photo 1, 18 September 2017
  • Harbour Views construction site, inspection photo 2, 18 September 2017
  • Harbour Views construction site, inspection photo 3, 18 September 2017
  • Harbour Views construction site, inspection photo 4, 18 September 2017

All 99 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Harbour Views?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Harbour Views handover date?
Construction of Harbour Views is recorded as complete, with a registered completion date of November 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Harbour Views?
Harbour Views was 100% built at the site inspection on 5 November 2020. The site has been inspected 11 times since December 2016. The Land Department took 99 site photos at its inspections.
Is Harbour Views delayed?
The register lists construction as complete.
Who is building Harbour Views?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Harbour Views?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.