Harbour Gate construction progress
The register lists Harbour Gate in Dubai Creek Harbour as complete, with a registered completion date of August 2022. Its last site inspection on record was in June 2022. The developer is The Lagoons Phase One.
100%
Built, at the site inspection of 22 June 2022
Construction complete
- Registered completion date
- August 2022
- Construction started
- February 2017
- First registered
- October 2016
- Developer
- The Lagoons Phase One
- Community
- Dubai Creek Harbour
- Units
- 517
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- هاربور جيت
- Project number
- 1818
- Site inspections
- 17
Schedule
The register lists Harbour Gate as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
22 June 2022
100%+2.2 pts
25 April 2022
98%+1.7 pts
6 January 2022
96%+2.1 pts
2 September 2021
94%+5.4 pts
9 May 2021
89%+3.5 pts
26 January 2021
85%+5.1 pts
8 October 2020
80%+7.8 pts
4 June 2020
72%+11 pts
28 January 2020
61%+10 pts
29 October 2019
51%+15 pts
Context
Dubai Creek Harbour has 14 projects under construction, 53% built on average.
The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Harbour Gate?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Harbour Gate handover date?
- Construction of Harbour Gate is recorded as complete, with a registered completion date of August 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Harbour Gate?
- Harbour Gate was 100% built at the site inspection on 22 June 2022. The site has been inspected 17 times since July 2017. The Land Department took 159 site photos at its inspections.
- Is Harbour Gate delayed?
- The register lists construction as complete.
- Who is building Harbour Gate?
- The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Harbour Gate?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Creek WatersAlso by The Lagoons Phase One. 81%, Due September 2027.
- Creek Waters 2Also by The Lagoons Phase One. 82%, Due December 2027.
- AeonNearby in Dubai Creek Harbour. 96%.
- OriaNearby in Dubai Creek Harbour. 89%.
- ValoNearby in Dubai Creek Harbour. 91%.
- ArloNearby in Dubai Creek Harbour. 72%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




