Creek Gate construction progress
The register lists Creek Gate in Dubai Creek Harbour as complete, with a registered completion date of November 2021. Its last site inspection on record was in November 2021. The developer is The Lagoons Phase One.
100%
Built, at the site inspection of 18 November 2021
Construction complete
- Registered completion date
- November 2021
- Construction started
- March 2017
- First registered
- September 2016
- Developer
- The Lagoons Phase One
- Community
- Dubai Creek Harbour
- Units
- 498
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- كريك جيت
- Project number
- 1813
- Site inspections
- 15
Schedule
The register lists Creek Gate as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
18 November 2021
100%+2.5 pts
23 September 2021
97%+1.9 pts
4 May 2021
96%+1.4 pts
20 January 2021
94%+4.2 pts
16 September 2020
90%+3.7 pts
4 June 2020
86%+8.3 pts
20 February 2020
78%+13 pts
29 October 2019
65%+18 pts
9 July 2019
47%+12 pts
11 April 2019
35%+13 pts
Context
Dubai Creek Harbour has 14 projects under construction, 53% built on average.
The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Creek Gate?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Creek Gate handover date?
- Construction of Creek Gate is recorded as complete, with a registered completion date of November 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Creek Gate?
- Creek Gate was 100% built at the site inspection on 18 November 2021. The site has been inspected 15 times since July 2017. The Land Department took 147 site photos at its inspections.
- Is Creek Gate delayed?
- The register lists construction as complete.
- Who is building Creek Gate?
- The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Creek Gate?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Creek WatersAlso by The Lagoons Phase One. 81%, Due September 2027.
- Creek Waters 2Also by The Lagoons Phase One. 82%, Due December 2027.
- AeonNearby in Dubai Creek Harbour. 96%.
- OriaNearby in Dubai Creek Harbour. 89%.
- ValoNearby in Dubai Creek Harbour. 91%.
- ArloNearby in Dubai Creek Harbour. 72%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)








