Creek Crescent construction progress

The register lists Creek Crescent in Dubai Creek Harbour as complete, with a registered completion date of March 2023. Its last site inspection on record was in January 2025. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 6 January 2025

Construction complete

Registered completion date
March 2023
Construction started
February 2020
First registered
February 2020
Units
230
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كريك كريسنت
Project number
2188
Site inspections
5

Schedule

The register lists Creek Crescent as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20212022202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 January 2025

100%+16 pts

  • Creek Crescent construction site, inspection photo 1, 6 January 2025
  • Creek Crescent construction site, inspection photo 2, 6 January 2025
  • Creek Crescent construction site, inspection photo 3, 6 January 2025
  • Creek Crescent construction site, inspection photo 4, 6 January 2025

16 August 2024

84%+23 pts

  • Creek Crescent construction site, inspection photo 1, 16 August 2024
  • Creek Crescent construction site, inspection photo 2, 16 August 2024
  • Creek Crescent construction site, inspection photo 3, 16 August 2024
  • Creek Crescent construction site, inspection photo 4, 16 August 2024

6 April 2024

61%+45 pts

  • Creek Crescent construction site, inspection photo 1, 6 April 2024
  • Creek Crescent construction site, inspection photo 2, 6 April 2024
  • Creek Crescent construction site, inspection photo 3, 6 April 2024
  • Creek Crescent construction site, inspection photo 4, 6 April 2024

18 September 2023

16%+9.9 pts

  • Creek Crescent construction site, inspection photo 1, 18 September 2023
  • Creek Crescent construction site, inspection photo 2, 18 September 2023
  • Creek Crescent construction site, inspection photo 3, 18 September 2023
  • Creek Crescent construction site, inspection photo 4, 18 September 2023

31 May 2023

6.1%

  • Creek Crescent construction site, inspection photo 1, 31 May 2023
  • Creek Crescent construction site, inspection photo 2, 31 May 2023
  • Creek Crescent construction site, inspection photo 3, 31 May 2023
  • Creek Crescent construction site, inspection photo 4, 31 May 2023

All 35 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Crescent?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Crescent handover date?
Construction of Creek Crescent is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Crescent?
Creek Crescent was 100% built at the site inspection on 6 January 2025. The site has been inspected 5 times since May 2023. The Land Department took 35 site photos at its inspections.
Is Creek Crescent delayed?
The register lists construction as complete.
Who is building Creek Crescent?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Crescent?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.