Skip to content

Creek Beach - Vida Residences construction progress

The register lists Creek Beach - Vida Residences in Dubai Creek Harbour as complete, with a registered completion date of April 2023. Its last site inspection on record was in May 2023. The developer is Dubai Creek Harbour.

100%

Built, at the site inspection of 15 May 2023

Construction complete

Registered completion date
April 2023
Construction started
September 2019
First registered
July 2019
Units
233
Escrow bank
Mashreq Bank
Name in Arabic
شاطىء الخور - فيدا رزيدنسز
Project number
2174
Site inspections
8

Schedule

The register lists Creek Beach - Vida Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 May 2023

100%+9.5 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 15 May 2023
  • Creek Beach - Vida Residences construction site, inspection photo 2, 15 May 2023
  • Creek Beach - Vida Residences construction site, inspection photo 3, 15 May 2023
  • Creek Beach - Vida Residences construction site, inspection photo 4, 15 May 2023

13 December 2022

91%+16 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 13 December 2022
  • Creek Beach - Vida Residences construction site, inspection photo 2, 13 December 2022
  • Creek Beach - Vida Residences construction site, inspection photo 3, 13 December 2022
  • Creek Beach - Vida Residences construction site, inspection photo 4, 13 December 2022

22 August 2022

74%+21 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 22 August 2022
  • Creek Beach - Vida Residences construction site, inspection photo 2, 22 August 2022
  • Creek Beach - Vida Residences construction site, inspection photo 3, 22 August 2022
  • Creek Beach - Vida Residences construction site, inspection photo 4, 22 August 2022

27 April 2022

53%+24 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 27 April 2022
  • Creek Beach - Vida Residences construction site, inspection photo 2, 27 April 2022
  • Creek Beach - Vida Residences construction site, inspection photo 3, 27 April 2022
  • Creek Beach - Vida Residences construction site, inspection photo 4, 27 April 2022

20 December 2021

28%+16 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 20 December 2021
  • Creek Beach - Vida Residences construction site, inspection photo 2, 20 December 2021
  • Creek Beach - Vida Residences construction site, inspection photo 3, 20 December 2021
  • Creek Beach - Vida Residences construction site, inspection photo 4, 20 December 2021

24 August 2021

13%+8.1 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 24 August 2021
  • Creek Beach - Vida Residences construction site, inspection photo 2, 24 August 2021
  • Creek Beach - Vida Residences construction site, inspection photo 3, 24 August 2021
  • Creek Beach - Vida Residences construction site, inspection photo 4, 24 August 2021

25 June 2020

4.6%+3.6 pts

  • Creek Beach - Vida Residences construction site, inspection photo 1, 25 June 2020
  • Creek Beach - Vida Residences construction site, inspection photo 2, 25 June 2020
  • Creek Beach - Vida Residences construction site, inspection photo 3, 25 June 2020

10 March 2020

1.0%

  • Creek Beach - Vida Residences construction site, inspection photo 1, 10 March 2020
  • Creek Beach - Vida Residences construction site, inspection photo 2, 10 March 2020
  • Creek Beach - Vida Residences construction site, inspection photo 3, 10 March 2020
  • Creek Beach - Vida Residences construction site, inspection photo 4, 10 March 2020

All 81 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Beach - Vida Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Beach - Vida Residences handover date?
Construction of Creek Beach - Vida Residences is recorded as complete, with a registered completion date of April 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Beach - Vida Residences?
Creek Beach - Vida Residences was 100% built at the site inspection on 15 May 2023. The site has been inspected 8 times since March 2020. The Land Department took 81 site photos at its inspections.
Is Creek Beach - Vida Residences delayed?
The register lists construction as complete.
Who is building Creek Beach - Vida Residences?
The registered developer is Dubai Creek Harbour. It has 15 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Beach - Vida Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.