Creek Beach - Rosewater construction progress
The register lists Creek Beach - Rosewater in Dubai Creek Harbour as complete, with a registered completion date of March 2023. Its last site inspection on record was in November 2024. The developer is Dubai Creek Harbour.
100%
Built, at the site inspection of 7 November 2024
Construction complete
- Registered completion date
- March 2023
- Construction started
- April 2020
- First registered
- October 2019
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour
- Units
- 211
- Escrow bank
- Mashreq Bank
- Name in Arabic
- شاطئ الخور - روز وتر
- Project number
- 2193
- Site inspections
- 8
Schedule
The register lists Creek Beach - Rosewater as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
7 November 2024
100%+4.9 pts
17 September 2024
95%+30 pts
6 March 2024
65%+28 pts
4 October 2023
37%+11 pts
14 June 2023
26%+15 pts
26 January 2023
11%+6.5 pts
13 October 2022
4.3%+0.2 pts
20 May 2022
4.0%
Context
Dubai Creek Harbour has 14 projects under construction, 53% built on average.
Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Creek Beach - Rosewater?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Creek Beach - Rosewater handover date?
- Construction of Creek Beach - Rosewater is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Creek Beach - Rosewater?
- Creek Beach - Rosewater was 100% built at the site inspection on 7 November 2024. The site has been inspected 8 times since May 2022. The Land Department took 62 site photos at its inspections.
- Is Creek Beach - Rosewater delayed?
- The register lists construction as complete.
- Who is building Creek Beach - Rosewater?
- The registered developer is Dubai Creek Harbour. It has 15 other projects under construction in Dubai.
- Which bank holds the escrow account for Creek Beach - Rosewater?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AeonAlso by Dubai Creek Harbour. 96%.
- OriaAlso by Dubai Creek Harbour. 89%.
- ValoAlso by Dubai Creek Harbour. 91%.
- ArloAlso by Dubai Creek Harbour. 72%.
- Creek WatersNearby in Dubai Creek Harbour. 81%, Due September 2027.
- Creek Waters 2Nearby in Dubai Creek Harbour. 82%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)