Skip to content

Creek Beach - Rosewater construction progress

The register lists Creek Beach - Rosewater in Dubai Creek Harbour as complete, with a registered completion date of March 2023. Its last site inspection on record was in November 2024. The developer is Dubai Creek Harbour.

100%

Built, at the site inspection of 7 November 2024

Construction complete

Registered completion date
March 2023
Construction started
April 2020
First registered
October 2019
Units
211
Escrow bank
Mashreq Bank
Name in Arabic
شاطئ الخور - روز وتر
Project number
2193
Site inspections
8

Schedule

The register lists Creek Beach - Rosewater as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2021202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 November 2024

100%+4.9 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 7 November 2024
  • Creek Beach - Rosewater construction site, inspection photo 2, 7 November 2024
  • Creek Beach - Rosewater construction site, inspection photo 3, 7 November 2024
  • Creek Beach - Rosewater construction site, inspection photo 4, 7 November 2024

17 September 2024

95%+30 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 17 September 2024
  • Creek Beach - Rosewater construction site, inspection photo 2, 17 September 2024
  • Creek Beach - Rosewater construction site, inspection photo 3, 17 September 2024
  • Creek Beach - Rosewater construction site, inspection photo 4, 17 September 2024

6 March 2024

65%+28 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 6 March 2024
  • Creek Beach - Rosewater construction site, inspection photo 2, 6 March 2024
  • Creek Beach - Rosewater construction site, inspection photo 3, 6 March 2024
  • Creek Beach - Rosewater construction site, inspection photo 4, 6 March 2024

4 October 2023

37%+11 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 4 October 2023
  • Creek Beach - Rosewater construction site, inspection photo 2, 4 October 2023
  • Creek Beach - Rosewater construction site, inspection photo 3, 4 October 2023
  • Creek Beach - Rosewater construction site, inspection photo 4, 4 October 2023

14 June 2023

26%+15 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 14 June 2023
  • Creek Beach - Rosewater construction site, inspection photo 2, 14 June 2023
  • Creek Beach - Rosewater construction site, inspection photo 3, 14 June 2023
  • Creek Beach - Rosewater construction site, inspection photo 4, 14 June 2023

26 January 2023

11%+6.5 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 26 January 2023
  • Creek Beach - Rosewater construction site, inspection photo 2, 26 January 2023
  • Creek Beach - Rosewater construction site, inspection photo 3, 26 January 2023
  • Creek Beach - Rosewater construction site, inspection photo 4, 26 January 2023

13 October 2022

4.3%+0.2 pts

  • Creek Beach - Rosewater construction site, inspection photo 1, 13 October 2022
  • Creek Beach - Rosewater construction site, inspection photo 2, 13 October 2022
  • Creek Beach - Rosewater construction site, inspection photo 3, 13 October 2022
  • Creek Beach - Rosewater construction site, inspection photo 4, 13 October 2022

20 May 2022

4.0%

  • Creek Beach - Rosewater construction site, inspection photo 1, 20 May 2022
  • Creek Beach - Rosewater construction site, inspection photo 2, 20 May 2022
  • Creek Beach - Rosewater construction site, inspection photo 3, 20 May 2022
  • Creek Beach - Rosewater construction site, inspection photo 4, 20 May 2022

All 62 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Beach - Rosewater?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Beach - Rosewater handover date?
Construction of Creek Beach - Rosewater is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Beach - Rosewater?
Creek Beach - Rosewater was 100% built at the site inspection on 7 November 2024. The site has been inspected 8 times since May 2022. The Land Department took 62 site photos at its inspections.
Is Creek Beach - Rosewater delayed?
The register lists construction as complete.
Who is building Creek Beach - Rosewater?
The registered developer is Dubai Creek Harbour. It has 15 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Beach - Rosewater?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.