Skip to content

Creek Beach - Bayshore construction progress

The register lists Creek Beach - Bayshore in Dubai Creek Harbour as complete, with a registered completion date of October 2022. Its last site inspection on record was in March 2023. The developer is Dubai Creek Harbour.

100%

Built, at the site inspection of 7 March 2023

Construction complete

Registered completion date
October 2022
Construction started
April 2019
First registered
March 2019
Units
305
Escrow bank
Mashreq Bank
Name in Arabic
شاطئ الخور - بيشور
Project number
2135
Site inspections
11

Schedule

The register lists Creek Beach - Bayshore as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 March 2023

100%+5.8 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 7 March 2023
  • Creek Beach - Bayshore construction site, inspection photo 2, 7 March 2023
  • Creek Beach - Bayshore construction site, inspection photo 3, 7 March 2023
  • Creek Beach - Bayshore construction site, inspection photo 4, 7 March 2023

22 November 2022

94%+4.1 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 22 November 2022
  • Creek Beach - Bayshore construction site, inspection photo 2, 22 November 2022
  • Creek Beach - Bayshore construction site, inspection photo 3, 22 November 2022
  • Creek Beach - Bayshore construction site, inspection photo 4, 22 November 2022

10 August 2022

90%+17 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 10 August 2022
  • Creek Beach - Bayshore construction site, inspection photo 2, 10 August 2022
  • Creek Beach - Bayshore construction site, inspection photo 3, 10 August 2022
  • Creek Beach - Bayshore construction site, inspection photo 4, 10 August 2022

19 April 2022

73%+21 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 19 April 2022
  • Creek Beach - Bayshore construction site, inspection photo 2, 19 April 2022
  • Creek Beach - Bayshore construction site, inspection photo 3, 19 April 2022
  • Creek Beach - Bayshore construction site, inspection photo 4, 19 April 2022

23 November 2021

52%+12 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 23 November 2021
  • Creek Beach - Bayshore construction site, inspection photo 2, 23 November 2021
  • Creek Beach - Bayshore construction site, inspection photo 3, 23 November 2021
  • Creek Beach - Bayshore construction site, inspection photo 4, 23 November 2021

19 August 2021

40%+14 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 19 August 2021
  • Creek Beach - Bayshore construction site, inspection photo 2, 19 August 2021
  • Creek Beach - Bayshore construction site, inspection photo 3, 19 August 2021
  • Creek Beach - Bayshore construction site, inspection photo 4, 19 August 2021

12 April 2021

26%+13 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 12 April 2021
  • Creek Beach - Bayshore construction site, inspection photo 2, 12 April 2021
  • Creek Beach - Bayshore construction site, inspection photo 3, 12 April 2021
  • Creek Beach - Bayshore construction site, inspection photo 4, 12 April 2021

23 December 2020

13%+4.9 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 23 December 2020
  • Creek Beach - Bayshore construction site, inspection photo 2, 23 December 2020
  • Creek Beach - Bayshore construction site, inspection photo 3, 23 December 2020
  • Creek Beach - Bayshore construction site, inspection photo 4, 23 December 2020

3 September 2020

8.3%+3.1 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 3 September 2020
  • Creek Beach - Bayshore construction site, inspection photo 2, 3 September 2020
  • Creek Beach - Bayshore construction site, inspection photo 3, 3 September 2020

16 February 2020

5.2%+5.0 pts

  • Creek Beach - Bayshore construction site, inspection photo 1, 16 February 2020
  • Creek Beach - Bayshore construction site, inspection photo 2, 16 February 2020
  • Creek Beach - Bayshore construction site, inspection photo 3, 16 February 2020

All 87 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Beach - Bayshore?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Beach - Bayshore handover date?
Construction of Creek Beach - Bayshore is recorded as complete, with a registered completion date of October 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Beach - Bayshore?
Creek Beach - Bayshore was 100% built at the site inspection on 7 March 2023. The site has been inspected 11 times since October 2019. The Land Department took 87 site photos at its inspections.
Is Creek Beach - Bayshore delayed?
The register lists construction as complete.
Who is building Creek Beach - Bayshore?
The registered developer is Dubai Creek Harbour. It has 15 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Beach - Bayshore?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.