Altus construction progress

Altus in Dubai Creek Harbour is 64% built at the Land Department inspection of June 2026. Developer Dubai Creek Harbour. Completion registered for January 2029.

64%

Built, at the Land Department site inspection of 25 June 2026

On pace for its date

Completion date (Land Department)
January 2029
Finish at recent pace
February 2027
Construction started
December 2024
Registered with the Land Department
August 2024
Units
283
Escrow bank
Mashreq Bank
Name in Arabic
ألتوس
Land Department project number
3184
Land Department site inspections
6

Schedule

Since October 2025 Altus has added about 4.9 points a month. That puts 100% around February 2027, within three months of its registered completion date of January 2029.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 June 2026

64%+13 pts

  • Altus construction site, Land Department inspection photo 1, 25 June 2026
  • Altus construction site, Land Department inspection photo 2, 25 June 2026
  • Altus construction site, Land Department inspection photo 3, 25 June 2026
  • Altus construction site, Land Department inspection photo 4, 25 June 2026

17 March 2026

52%+21 pts

  • Altus construction site, Land Department inspection photo 1, 17 March 2026
  • Altus construction site, Land Department inspection photo 2, 17 March 2026
  • Altus construction site, Land Department inspection photo 3, 17 March 2026
  • Altus construction site, Land Department inspection photo 4, 17 March 2026

4 December 2025

31%+6.8 pts

  • Altus construction site, Land Department inspection photo 1, 4 December 2025
  • Altus construction site, Land Department inspection photo 2, 4 December 2025
  • Altus construction site, Land Department inspection photo 3, 4 December 2025
  • Altus construction site, Land Department inspection photo 4, 4 December 2025

21 October 2025

24%+14 pts

  • Altus construction site, Land Department inspection photo 1, 21 October 2025
  • Altus construction site, Land Department inspection photo 2, 21 October 2025
  • Altus construction site, Land Department inspection photo 3, 21 October 2025
  • Altus construction site, Land Department inspection photo 4, 21 October 2025

23 May 2025

9.9%+9.9 pts

  • Altus construction site, Land Department inspection photo 1, 23 May 2025
  • Altus construction site, Land Department inspection photo 2, 23 May 2025
  • Altus construction site, Land Department inspection photo 3, 23 May 2025
  • Altus construction site, Land Department inspection photo 4, 23 May 2025

2 August 2024

0%

  • Altus construction site, Land Department inspection photo 1, 2 August 2024
  • Altus construction site, Land Department inspection photo 2, 2 August 2024

All 35 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 41% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Altus?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Altus be completed?
The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Altus is built?
64%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 6 times since August 2024.
Is Altus delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2029.
Who is building Altus?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Altus?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.