Altus construction progress
The registered completion date for Altus in Dubai Creek Harbour is January 2029. At the last site inspection, in November 2026, it was 87% built. The developer is Dubai Creek Harbour.
87%
Built, at the site inspection of 10 November 2026
On pace for its date
- Registered completion date
- January 2029
- Finish at recent pace
- February 2027
- Construction started
- December 2024
- First registered
- August 2024
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour
- Units
- 283
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ألتوس
- Project number
- 3184
- Site inspections
- 7
Schedule
Since December 2025 Altus has added about 4.9 points a month. That puts 100% around February 2027, within three months of its registered completion date of January 2029.
Site inspections
10 November 2026
87%+22 pts
25 June 2026
64%+13 pts
17 March 2026
52%+21 pts
4 December 2025
31%+6.8 pts
21 October 2025
24%+14 pts
23 May 2025
9.9%+9.9 pts
2 August 2024
0%
Context
Dubai Creek Harbour has 14 projects under construction, 53% built on average.
Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Altus?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Altus handover date?
- The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Altus?
- Altus was 87% built at the site inspection on 10 November 2026. The site has been inspected 7 times since August 2024. The Land Department took 44 site photos at its inspections.
- Is Altus delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2029.
- Who is building Altus?
- The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
- Which bank holds the escrow account for Altus?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AeonAlso by Dubai Creek Harbour. 96%.
- OriaAlso by Dubai Creek Harbour. 89%.
- ValoAlso by Dubai Creek Harbour. 91%.
- ArloAlso by Dubai Creek Harbour. 72%.
- Creek WatersNearby in Dubai Creek Harbour. 81%, Due September 2027.
- Creek Waters 2Nearby in Dubai Creek Harbour. 82%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.