Altus construction progress

The registered completion date for Altus in Dubai Creek Harbour is January 2029. At the last site inspection, in November 2026, it was 87% built. The developer is Dubai Creek Harbour.

87%

Built, at the site inspection of 10 November 2026

On pace for its date

Registered completion date
January 2029
Finish at recent pace
February 2027
Construction started
December 2024
First registered
August 2024
Units
283
Escrow bank
Mashreq Bank
Name in Arabic
ألتوس
Project number
3184
Site inspections
7

Schedule

Since December 2025 Altus has added about 4.9 points a month. That puts 100% around February 2027, within three months of its registered completion date of January 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

87%+22 pts

  • Altus construction site, inspection photo 1, 10 November 2026
  • Altus construction site, inspection photo 2, 10 November 2026
  • Altus construction site, inspection photo 3, 10 November 2026
  • Altus construction site, inspection photo 4, 10 November 2026

25 June 2026

64%+13 pts

  • Altus construction site, inspection photo 1, 25 June 2026
  • Altus construction site, inspection photo 2, 25 June 2026
  • Altus construction site, inspection photo 3, 25 June 2026
  • Altus construction site, inspection photo 4, 25 June 2026

17 March 2026

52%+21 pts

  • Altus construction site, inspection photo 1, 17 March 2026
  • Altus construction site, inspection photo 2, 17 March 2026
  • Altus construction site, inspection photo 3, 17 March 2026
  • Altus construction site, inspection photo 4, 17 March 2026

4 December 2025

31%+6.8 pts

  • Altus construction site, inspection photo 1, 4 December 2025
  • Altus construction site, inspection photo 2, 4 December 2025
  • Altus construction site, inspection photo 3, 4 December 2025
  • Altus construction site, inspection photo 4, 4 December 2025

21 October 2025

24%+14 pts

  • Altus construction site, inspection photo 1, 21 October 2025
  • Altus construction site, inspection photo 2, 21 October 2025
  • Altus construction site, inspection photo 3, 21 October 2025
  • Altus construction site, inspection photo 4, 21 October 2025

23 May 2025

9.9%+9.9 pts

  • Altus construction site, inspection photo 1, 23 May 2025
  • Altus construction site, inspection photo 2, 23 May 2025
  • Altus construction site, inspection photo 3, 23 May 2025
  • Altus construction site, inspection photo 4, 23 May 2025

2 August 2024

0%

  • Altus construction site, inspection photo 1, 2 August 2024
  • Altus construction site, inspection photo 2, 2 August 2024

All 44 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Altus?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Altus handover date?
The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Altus?
Altus was 87% built at the site inspection on 10 November 2026. The site has been inspected 7 times since August 2024. The Land Department took 44 site photos at its inspections.
Is Altus delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2029.
Who is building Altus?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Altus?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.