Albero construction progress
The registered completion date for Albero in Dubai Creek Harbour is September 2029. At the last site inspection, in July 2026, it was 11% built. The developer is Dubai Creek Harbour.
11%
Built, at the site inspection of 2 July 2026
Running behind its date
- Registered completion date
- September 2029
- Finish at recent pace
- April 2036
- Construction started
- June 2025
- First registered
- March 2025
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour
- Units
- 479
- Escrow bank
- Emirates NBD
- Name in Arabic
- البيرو
- Project number
- 3609
- Site inspections
- 5
Schedule
Between September 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of September 2029.
Site inspections
2 July 2026
11%+1.8 pts
17 March 2026
9.2%+1.9 pts
30 December 2025
7.3%+3.4 pts
19 September 2025
3.9%+3.9 pts
17 March 2025
0%
Context
Dubai Creek Harbour has 14 projects under construction, 53% built on average.
Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Albero?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Albero handover date?
- The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Albero?
- Albero was 11% built at the site inspection on 2 July 2026. The site has been inspected 5 times since March 2025. The Land Department took 18 site photos at its inspections.
- Is Albero delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
- Who is building Albero?
- The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
- Which bank holds the escrow account for Albero?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AeonAlso by Dubai Creek Harbour. 96%.
- OriaAlso by Dubai Creek Harbour. 89%.
- ValoAlso by Dubai Creek Harbour. 91%.
- ArloAlso by Dubai Creek Harbour. 72%.
- Creek WatersNearby in Dubai Creek Harbour. 81%, Due September 2027.
- Creek Waters 2Nearby in Dubai Creek Harbour. 82%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)