Albero construction progress

The registered completion date for Albero in Dubai Creek Harbour is September 2029. At the last site inspection, in July 2026, it was 11% built. The developer is Dubai Creek Harbour.

11%

Built, at the site inspection of 2 July 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
April 2036
Construction started
June 2025
First registered
March 2025
Units
479
Escrow bank
Emirates NBD
Name in Arabic
البيرو
Project number
3609
Site inspections
5

Schedule

Between September 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of September 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 July 2026

11%+1.8 pts

  • Albero construction site, inspection photo 1, 2 July 2026
  • Albero construction site, inspection photo 2, 2 July 2026
  • Albero construction site, inspection photo 3, 2 July 2026

17 March 2026

9.2%+1.9 pts

  • Albero construction site, inspection photo 1, 17 March 2026
  • Albero construction site, inspection photo 2, 17 March 2026

30 December 2025

7.3%+3.4 pts

  • Albero construction site, inspection photo 1, 30 December 2025
  • Albero construction site, inspection photo 2, 30 December 2025
  • Albero construction site, inspection photo 3, 30 December 2025

19 September 2025

3.9%+3.9 pts

  • Albero construction site, inspection photo 1, 19 September 2025
  • Albero construction site, inspection photo 2, 19 September 2025
  • Albero construction site, inspection photo 3, 19 September 2025
  • Albero construction site, inspection photo 4, 19 September 2025

17 March 2025

0%

  • Albero construction site, inspection photo 1, 17 March 2025
  • Albero construction site, inspection photo 2, 17 March 2025

All 18 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Albero?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Albero handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Albero?
Albero was 11% built at the site inspection on 2 July 2026. The site has been inspected 5 times since March 2025. The Land Department took 18 site photos at its inspections.
Is Albero delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Albero?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Albero?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.