The Palm - Jebel Ali Co projects under construction
The Palm - Jebel Ali Co has 22 projects under construction in Dubai, according to the Dubai Land Department. On average they are 15% built. The next one due is Palm Jebel Ali - Frond O, in September 2027.
- Palm Jebel Ali - Frond OPalm Jabal Ali56%Due September 2027
- Palm Jebel Ali - Frond KPalm Jabal Ali48%No date set
- Palm Jebel Ali - Frond NPalm Jabal Ali47%Due October 2027
- Palm Jebel Ali - Frond LPalm Jabal Ali43%No date set
- Palm Jebel Ali - Frond MPalm Jabal Ali40%Due October 2027
- Palm Jebel Ali - Frond PPalm Jabal Ali35%Due September 2027
- Palm Jebel Ali - Frond FPalm Jabal Ali12%Due January 2028
- Palm Jebel Ali - Frond APalm Jabal Ali11%No date set
- Palm Jebel Ali - Frond BPalm Jabal Ali10%Due January 2028
- Palm Jebel Ali - Frond EPalm Jabal Ali9.2%Due January 2028
- Palm Jebel Ali - Frond DPalm Jabal Ali8.7%Due January 2028
- Palm Jebel Ali - Frond CPalm Jabal Ali8.6%Due January 2028
- Palm Jebel Ali - The Beach And Coral Collection - Frond BPalm Jabal Ali1.7%Due December 2028
- Palm Jebel Ali - The Beach And Coral Collection - Frond CPalm Jabal Ali1.7%No date set
- Palm Jebel Ali - The Beach And Coral Collection - Frond DPalm Jabal Ali1.6%No date set
- Palm Jebel Ali - The Beach And Coral CollectionPalm Jabal Ali1.6%Due December 2028
- Palm Jebel Ali - The Beach And Coral Collection - Frond EPalm Jabal Ali1.4%No date set
- Palm Jebel Ali - The Beach And Coral Collection - Frond FPalm Jabal Ali1.3%Due December 2028
- Palm Central Private Residences - Frond M0.1%Due July 2029
- Palm Central Private Residences - Frond N0%No date set
- Palm Jebel Ali - Frond IPalm Jabal Ali0%No date set
- Palm Jebel Ali - Frond JPalm Jabal Ali0%No date set
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.