Palm Jebel Ali - The Beach And Coral Collection construction progress
Palm Jebel Ali - The Beach And Coral Collection in Palm Jabal Ali is 1.6% built at the Land Department inspection of July 2026. Developer The Palm - Jebel Ali Co. Completion registered for December 2028.
1.6%
Built, at the Land Department site inspection of 13 July 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- May 2078
- Construction started
- December 2025
- Registered with the Land Department
- October 2025
- Developer
- The Palm - Jebel Ali Co
- Community
- Palm Jabal Ali
- Units
- 44
- Escrow bank
- National Bank of Ras Al Khaimah
- Name in Arabic
- نخلة جبل علي - ذا بيتش آند كورال كوليكشن
- Land Department project number
- 4091
- Land Department site inspections
- 3
Schedule
Between September 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around May 2078, more than three months after the December 2028 date registered with the Land Department.
Site inspections
13 July 2026
1.6%+0.5 pts
28 April 2026
1.1%+1.1 pts
16 September 2025
0%
Context
Palm Jabal Ali has 20 projects under construction, 17% built on average.
The Palm - Jebel Ali Co has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Palm Jebel Ali - The Beach And Coral Collection?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Palm Jebel Ali - The Beach And Coral Collection be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around May 2078. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Palm Jebel Ali - The Beach And Coral Collection is built?
- 1.6%, measured at the Land Department site inspection on 13 July 2026. The Land Department engineers have inspected the site 3 times since September 2025.
- Is Palm Jebel Ali - The Beach And Coral Collection delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Palm Jebel Ali - The Beach And Coral Collection?
- The registered developer is The Palm - Jebel Ali Co. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Palm Jebel Ali - The Beach And Coral Collection?
- National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Jebel Ali - Frond PAlso by The Palm - Jebel Ali Co. 35%, Due September 2027.
- Palm Jebel Ali - Frond OAlso by The Palm - Jebel Ali Co. 56%, Due September 2027.
- Palm Jebel Ali - Frond NAlso by The Palm - Jebel Ali Co. 47%, Due October 2027.
- Palm Jebel Ali - Frond MAlso by The Palm - Jebel Ali Co. 40%, Due October 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.







