Palm Jebel Ali - The Beach And Coral Collection - Frond E construction progress

The registered completion date for Palm Jebel Ali - The Beach And Coral Collection - Frond E in Palm Jabal Ali is December 2028. At the last site inspection, in October 2026, it was 2.6% built. The developer is The Palm - Jebel Ali Co.

2.6%

Built, at the site inspection of 13 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
September 2052
Construction started
December 2025
First registered
October 2025
Units
40
Escrow bank
Mashreq Bank
Name in Arabic
E نخلة جبل علي - ذا بيتش آند كورال كوليكشن - السعفة
Project number
4113
Site inspections
4

Schedule

Between April 2026 and October 2026 the site added about 0.3 points a month. At that rate it would finish around September 2052, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

2.6%+1.2 pts

  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 1, 13 October 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 2, 13 October 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 3, 13 October 2026

13 July 2026

1.4%+0.5 pts

  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 1, 13 July 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 2, 13 July 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 3, 13 July 2026

28 April 2026

0.9%+0.9 pts

  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 1, 28 April 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 2, 28 April 2026
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 3, 28 April 2026

22 September 2025

0%

  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 1, 22 September 2025
  • Palm Jebel Ali - The Beach And Coral Collection - Frond E construction site, inspection photo 2, 22 September 2025

All 11 site photos, by inspection date

Context

Palm Jabal Ali has 20 projects under construction, 21% built on average.

The Palm - Jebel Ali Co has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palm Jebel Ali - The Beach And Coral Collection - Frond E?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Palm Jebel Ali - The Beach And Coral Collection - Frond E handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2052. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Palm Jebel Ali - The Beach And Coral Collection - Frond E?
Palm Jebel Ali - The Beach And Coral Collection - Frond E was 2.6% built at the site inspection on 13 October 2026. The site has been inspected 4 times since September 2025. The Land Department took 11 site photos at its inspections.
Is Palm Jebel Ali - The Beach And Coral Collection - Frond E delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Palm Jebel Ali - The Beach And Coral Collection - Frond E?
The registered developer is The Palm - Jebel Ali Co. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Palm Jebel Ali - The Beach And Coral Collection - Frond E?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.