Palm Jebel Ali - Frond F construction progress
The registered completion date for Palm Jebel Ali - Frond F in Palm Jabal Ali is January 2028. At the last site inspection, in September 2026, it was 12% built. The developer is The Palm - Jebel Ali Co.
12%
Built, at the site inspection of 28 September 2026
Running behind its date
- Registered completion date
- January 2028
- Finish at recent pace
- October 2033
- Construction started
- January 2025
- First registered
- November 2024
- Developer
- The Palm - Jebel Ali Co
- Community
- Palm Jabal Ali
- Units
- 80
- Escrow bank
- Emirates NBD
- Name in Arabic
- F نخلة جبل علي - السعفة
- Project number
- 3354
- Site inspections
- 7
Schedule
Between November 2025 and September 2026 the site added about 1.0 points a month. At that rate it would finish around October 2033, more than three months after its registered date of January 2028.
Site inspections
28 September 2026
12%+7.5 pts
18 June 2026
4.3%+2.5 pts
16 March 2026
1.8%+0.8 pts
14 November 2025
1.0%+0.6 pts
21 August 2025
0.4%+0.2 pts
28 May 2025
0.2%+0.2 pts
23 October 2024
0%
Context
Palm Jabal Ali has 20 projects under construction, 21% built on average.
The Palm - Jebel Ali Co has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Palm Jebel Ali - Frond F?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Palm Jebel Ali - Frond F handover date?
- The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Palm Jebel Ali - Frond F?
- Palm Jebel Ali - Frond F was 12% built at the site inspection on 28 September 2026. The site has been inspected 7 times since October 2024. The Land Department took 29 site photos at its inspections.
- Is Palm Jebel Ali - Frond F delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
- Who is building Palm Jebel Ali - Frond F?
- The registered developer is The Palm - Jebel Ali Co. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Palm Jebel Ali - Frond F?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Jebel Ali - Frond PAlso by The Palm - Jebel Ali Co. 49%, Due September 2027.
- Palm Jebel Ali - Frond OAlso by The Palm - Jebel Ali Co. 68%, Due September 2027.
- Palm Jebel Ali - Frond NAlso by The Palm - Jebel Ali Co. 58%, Due October 2027.
- Palm Jebel Ali - Frond MAlso by The Palm - Jebel Ali Co. 51%, Due October 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)