Palm Jebel Ali - Frond D construction progress

The registered completion date for Palm Jebel Ali - Frond D in Palm Jabal Ali is January 2028. At the last site inspection, in September 2026, it was 8.7% built. The developer is The Palm - Jebel Ali Co.

8.7%

Built, at the site inspection of 28 September 2026

Running behind its date

Registered completion date
January 2028
Finish at recent pace
January 2037
Construction started
January 2025
First registered
November 2024
Units
116
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
D نخلة جبل علي - السعفة
Project number
3395
Site inspections
7

Schedule

Between November 2025 and September 2026 the site added about 0.7 points a month. At that rate it would finish around January 2037, more than three months after its registered date of January 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 September 2026

8.7%+4.5 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 28 September 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 28 September 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 28 September 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 4, 28 September 2026

18 June 2026

4.2%+2.2 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 18 June 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 18 June 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 18 June 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 4, 18 June 2026

16 March 2026

2.1%+1.1 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 16 March 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 16 March 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 16 March 2026
  • Palm Jebel Ali - Frond D construction site, inspection photo 4, 16 March 2026

14 November 2025

1.0%+0.5 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 14 November 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 14 November 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 14 November 2025

21 August 2025

0.5%+0.2 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 21 August 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 21 August 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 21 August 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 4, 21 August 2025

28 May 2025

0.3%+0.3 pts

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 28 May 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 28 May 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 3, 28 May 2025
  • Palm Jebel Ali - Frond D construction site, inspection photo 4, 28 May 2025

12 November 2024

0%

  • Palm Jebel Ali - Frond D construction site, inspection photo 1, 12 November 2024
  • Palm Jebel Ali - Frond D construction site, inspection photo 2, 12 November 2024

All 30 site photos, by inspection date

Context

Palm Jabal Ali has 20 projects under construction, 21% built on average.

The Palm - Jebel Ali Co has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palm Jebel Ali - Frond D?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Palm Jebel Ali - Frond D handover date?
The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Palm Jebel Ali - Frond D?
Palm Jebel Ali - Frond D was 8.7% built at the site inspection on 28 September 2026. The site has been inspected 7 times since November 2024. The Land Department took 30 site photos at its inspections.
Is Palm Jebel Ali - Frond D delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Palm Jebel Ali - Frond D?
The registered developer is The Palm - Jebel Ali Co. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Palm Jebel Ali - Frond D?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.