Palm Jebel Ali - Frond P construction progress

The registered completion date for Palm Jebel Ali - Frond P in Palm Jabal Ali is September 2027. At the last site inspection, in November 2026, it was 49% built. The developer is The Palm - Jebel Ali Co.

49%

Built, at the site inspection of 10 November 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
January 2028
Construction started
September 2023
First registered
May 2023
Units
90
Escrow bank
Emirates NBD
Name in Arabic
P نخلة جبل علي - السعفة
Project number
2590
Site inspections
8

Schedule

Between January 2026 and November 2026 the site added about 3.5 points a month. At that rate it would finish around January 2028, more than three months after its registered date of September 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

49%+14 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 10 November 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 10 November 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 10 November 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 10 November 2026

4 August 2026

35%+8.0 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 4 August 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 4 August 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 4 August 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 4 August 2026

30 April 2026

27%+11 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 30 April 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 30 April 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 30 April 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 30 April 2026

27 January 2026

16%+10 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 27 January 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 27 January 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 27 January 2026
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 27 January 2026

23 October 2025

5.4%+3.8 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 23 October 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 23 October 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 23 October 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 23 October 2025

23 July 2025

1.6%+0.8 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 23 July 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 23 July 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 23 July 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 23 July 2025

28 March 2025

0.8%+0.8 pts

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 28 March 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 28 March 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 28 March 2025
  • Palm Jebel Ali - Frond P construction site, inspection photo 4, 28 March 2025

2 March 2023

0%

  • Palm Jebel Ali - Frond P construction site, inspection photo 1, 2 March 2023
  • Palm Jebel Ali - Frond P construction site, inspection photo 2, 2 March 2023
  • Palm Jebel Ali - Frond P construction site, inspection photo 3, 2 March 2023

All 53 site photos, by inspection date

Context

Palm Jabal Ali has 20 projects under construction, 21% built on average.

The Palm - Jebel Ali Co has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palm Jebel Ali - Frond P?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Palm Jebel Ali - Frond P handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Palm Jebel Ali - Frond P?
Palm Jebel Ali - Frond P was 49% built at the site inspection on 10 November 2026. The site has been inspected 8 times since March 2023. The Land Department took 53 site photos at its inspections.
Is Palm Jebel Ali - Frond P delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Palm Jebel Ali - Frond P?
The registered developer is The Palm - Jebel Ali Co. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Palm Jebel Ali - Frond P?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.