Design Quarter construction photos

70 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Design Quarter was built on the day of each visit.

28 September 202641% built

30 June 202631% built

26 March 202626% built

7 November 202517% built

30 July 202514% built

2 May 20258.5% built

7 February 20254.8% built

3 June 20243.1% built

8 March 20230.9% built

Back to Design Quarter construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.