Vera Tower construction progress

The register lists Vera Tower in Business Bay as complete, with a registered completion date of March 2022. Its last site inspection on record was in March 2022. The developer is Damac World Real Estate.

100%

Built, at the site inspection of 31 March 2022

Construction complete

Registered completion date
March 2022
Construction started
December 2016
First registered
August 2016
Developer
Damac World Real Estate
Community
Business Bay
Units
526
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيرا تاور
Project number
1786
Site inspections
12

Schedule

The register lists Vera Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201720192021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 March 2022

100%+9.9 pts

  • Vera Tower construction site, inspection photo 1, 31 March 2022
  • Vera Tower construction site, inspection photo 2, 31 March 2022
  • Vera Tower construction site, inspection photo 3, 31 March 2022
  • Vera Tower construction site, inspection photo 4, 31 March 2022

14 September 2021

90%+17 pts

  • Vera Tower construction site, inspection photo 1, 14 September 2021
  • Vera Tower construction site, inspection photo 2, 14 September 2021
  • Vera Tower construction site, inspection photo 3, 14 September 2021
  • Vera Tower construction site, inspection photo 4, 14 September 2021

1 April 2021

73%+7.0 pts

  • Vera Tower construction site, inspection photo 1, 1 April 2021
  • Vera Tower construction site, inspection photo 2, 1 April 2021
  • Vera Tower construction site, inspection photo 3, 1 April 2021
  • Vera Tower construction site, inspection photo 4, 1 April 2021

22 September 2020

66%+23 pts

  • Vera Tower construction site, inspection photo 1, 22 September 2020
  • Vera Tower construction site, inspection photo 2, 22 September 2020
  • Vera Tower construction site, inspection photo 3, 22 September 2020
  • Vera Tower construction site, inspection photo 4, 22 September 2020

28 April 2020

43%+20 pts

  • Vera Tower construction site, inspection photo 1, 28 April 2020
  • Vera Tower construction site, inspection photo 2, 28 April 2020
  • Vera Tower construction site, inspection photo 3, 28 April 2020
  • Vera Tower construction site, inspection photo 4, 28 April 2020

19 December 2019

22%+8.7 pts

  • Vera Tower construction site, inspection photo 1, 19 December 2019
  • Vera Tower construction site, inspection photo 2, 19 December 2019
  • Vera Tower construction site, inspection photo 3, 19 December 2019
  • Vera Tower construction site, inspection photo 4, 19 December 2019

20 August 2019

13%+6.2 pts

  • Vera Tower construction site, inspection photo 1, 20 August 2019
  • Vera Tower construction site, inspection photo 2, 20 August 2019
  • Vera Tower construction site, inspection photo 3, 20 August 2019
  • Vera Tower construction site, inspection photo 4, 20 August 2019

3 April 2019

7.2%+2.2 pts

  • Vera Tower construction site, inspection photo 1, 3 April 2019
  • Vera Tower construction site, inspection photo 2, 3 April 2019
  • Vera Tower construction site, inspection photo 3, 3 April 2019
  • Vera Tower construction site, inspection photo 4, 3 April 2019

7 November 2018

5.0%+3.0 pts

  • Vera Tower construction site, inspection photo 1, 7 November 2018
  • Vera Tower construction site, inspection photo 2, 7 November 2018
  • Vera Tower construction site, inspection photo 3, 7 November 2018
  • Vera Tower construction site, inspection photo 4, 7 November 2018

6 June 2018

2.0%+1.8 pts

  • Vera Tower construction site, inspection photo 1, 6 June 2018
  • Vera Tower construction site, inspection photo 2, 6 June 2018
  • Vera Tower construction site, inspection photo 3, 6 June 2018
  • Vera Tower construction site, inspection photo 4, 6 June 2018

All 98 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Vera Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vera Tower handover date?
Construction of Vera Tower is recorded as complete, with a registered completion date of March 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vera Tower?
Vera Tower was 100% built at the site inspection on 31 March 2022. The site has been inspected 12 times since August 2017. The Land Department took 98 site photos at its inspections.
Is Vera Tower delayed?
The register lists construction as complete.
Who is building Vera Tower?
The registered developer is Damac World Real Estate.
Which bank holds the escrow account for Vera Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.