Upside Living construction progress

The register lists Upside Living in Business Bay as complete, with a registered completion date of February 2023. Its last site inspection on record was in August 2023. The developer is Srg Real Estate Developer.

100%

Built, at the site inspection of 11 August 2023

Construction complete

Registered completion date
February 2023
Construction started
December 2018
First registered
June 2019
Developer
Srg Real Estate Developer
Community
Business Bay
Units
527
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
آبسايد ليفينج
Project number
2164
Site inspections
7

Schedule

The register lists Upside Living as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 August 2023

100%+13 pts

  • Upside Living construction site, inspection photo 1, 11 August 2023
  • Upside Living construction site, inspection photo 2, 11 August 2023
  • Upside Living construction site, inspection photo 3, 11 August 2023
  • Upside Living construction site, inspection photo 4, 11 August 2023

16 December 2022

87%+4.5 pts

  • Upside Living construction site, inspection photo 1, 16 December 2022
  • Upside Living construction site, inspection photo 2, 16 December 2022
  • Upside Living construction site, inspection photo 3, 16 December 2022
  • Upside Living construction site, inspection photo 4, 16 December 2022

23 May 2022

83%+7.8 pts

  • Upside Living construction site, inspection photo 1, 23 May 2022
  • Upside Living construction site, inspection photo 2, 23 May 2022
  • Upside Living construction site, inspection photo 3, 23 May 2022
  • Upside Living construction site, inspection photo 4, 23 May 2022

22 December 2021

75%+7.4 pts

  • Upside Living construction site, inspection photo 1, 22 December 2021
  • Upside Living construction site, inspection photo 2, 22 December 2021
  • Upside Living construction site, inspection photo 3, 22 December 2021
  • Upside Living construction site, inspection photo 4, 22 December 2021

8 July 2021

67%+27 pts

  • Upside Living construction site, inspection photo 1, 8 July 2021
  • Upside Living construction site, inspection photo 2, 8 July 2021
  • Upside Living construction site, inspection photo 3, 8 July 2021
  • Upside Living construction site, inspection photo 4, 8 July 2021

3 August 2020

41%+24 pts

  • Upside Living construction site, inspection photo 1, 3 August 2020
  • Upside Living construction site, inspection photo 2, 3 August 2020
  • Upside Living construction site, inspection photo 3, 3 August 2020
  • Upside Living construction site, inspection photo 4, 3 August 2020

23 December 2019

17%

  • Upside Living construction site, inspection photo 1, 23 December 2019
  • Upside Living construction site, inspection photo 2, 23 December 2019
  • Upside Living construction site, inspection photo 3, 23 December 2019
  • Upside Living construction site, inspection photo 4, 23 December 2019

All 67 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Srg Real Estate Developer has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Upside Living?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Upside Living handover date?
Construction of Upside Living is recorded as complete, with a registered completion date of February 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Upside Living?
Upside Living was 100% built at the site inspection on 11 August 2023. The site has been inspected 7 times since December 2019. The Land Department took 67 site photos at its inspections.
Is Upside Living delayed?
The register lists construction as complete.
Who is building Upside Living?
The registered developer is Srg Real Estate Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Upside Living?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.