The Sterling East House construction progress

The register lists The Sterling East House in Business Bay as complete, with a registered completion date of August 2023. Its last site inspection on record was in August 2023. The developer is Op 17 Limited.

100%

Built, at the site inspection of 29 August 2023

Construction complete

Registered completion date
August 2023
Construction started
January 2009
First registered
April 2011
Developer
Op 17 Limited
Community
Business Bay
Units
234
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بيت الشرق الشرقي
Project number
1309
Site inspections
19

Schedule

The register lists The Sterling East House as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20102013201620192022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 August 2023

100%+8.9 pts

  • The Sterling East House construction site, inspection photo 1, 29 August 2023
  • The Sterling East House construction site, inspection photo 2, 29 August 2023
  • The Sterling East House construction site, inspection photo 3, 29 August 2023
  • The Sterling East House construction site, inspection photo 4, 29 August 2023

30 November 2022

91%+10 pts

  • The Sterling East House construction site, inspection photo 1, 30 November 2022
  • The Sterling East House construction site, inspection photo 2, 30 November 2022
  • The Sterling East House construction site, inspection photo 3, 30 November 2022
  • The Sterling East House construction site, inspection photo 4, 30 November 2022

2 June 2022

81%+2.4 pts

  • The Sterling East House construction site, inspection photo 1, 2 June 2022
  • The Sterling East House construction site, inspection photo 2, 2 June 2022
  • The Sterling East House construction site, inspection photo 3, 2 June 2022
  • The Sterling East House construction site, inspection photo 4, 2 June 2022

24 March 2022

79%+6.4 pts

  • The Sterling East House construction site, inspection photo 1, 24 March 2022
  • The Sterling East House construction site, inspection photo 2, 24 March 2022
  • The Sterling East House construction site, inspection photo 3, 24 March 2022
  • The Sterling East House construction site, inspection photo 4, 24 March 2022

7 December 2021

72%+2.0 pts

  • The Sterling East House construction site, inspection photo 1, 7 December 2021
  • The Sterling East House construction site, inspection photo 2, 7 December 2021
  • The Sterling East House construction site, inspection photo 3, 7 December 2021
  • The Sterling East House construction site, inspection photo 4, 7 December 2021

26 October 2021

70%

  • The Sterling East House construction site, inspection photo 1, 26 October 2021
  • The Sterling East House construction site, inspection photo 2, 26 October 2021
  • The Sterling East House construction site, inspection photo 3, 26 October 2021
  • The Sterling East House construction site, inspection photo 4, 26 October 2021

16 July 2020

71%

  • The Sterling East House construction site, inspection photo 1, 16 July 2020
  • The Sterling East House construction site, inspection photo 2, 16 July 2020
  • The Sterling East House construction site, inspection photo 3, 16 July 2020
  • The Sterling East House construction site, inspection photo 4, 16 July 2020

1 March 2020

71%+9.7 pts

  • The Sterling East House construction site, inspection photo 1, 1 March 2020
  • The Sterling East House construction site, inspection photo 2, 1 March 2020
  • The Sterling East House construction site, inspection photo 3, 1 March 2020
  • The Sterling East House construction site, inspection photo 4, 1 March 2020

9 July 2019

61%+11 pts

  • The Sterling East House construction site, inspection photo 1, 9 July 2019
  • The Sterling East House construction site, inspection photo 2, 9 July 2019
  • The Sterling East House construction site, inspection photo 3, 9 July 2019
  • The Sterling East House construction site, inspection photo 4, 9 July 2019

28 February 2019

50%+19 pts

  • The Sterling East House construction site, inspection photo 1, 28 February 2019
  • The Sterling East House construction site, inspection photo 2, 28 February 2019
  • The Sterling East House construction site, inspection photo 3, 28 February 2019
  • The Sterling East House construction site, inspection photo 4, 28 February 2019

All 169 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in The Sterling East House?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Sterling East House handover date?
Construction of The Sterling East House is recorded as complete, with a registered completion date of August 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Sterling East House?
The Sterling East House was 100% built at the site inspection on 29 August 2023. The site has been inspected 19 times since July 2014. The Land Department took 169 site photos at its inspections.
Is The Sterling East House delayed?
The register lists construction as complete.
Who is building The Sterling East House?
The registered developer is Op 17 Limited.
Which bank holds the escrow account for The Sterling East House?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.