The Binary By Omniyat construction progress

The register lists The Binary By Omniyat in Business Bay as complete, with a registered completion date of April 2015. Its last site inspection on record was in September 2015. The developer is Binary Development Limited.

100%

Built, at the site inspection of 30 September 2015

Construction complete

Registered completion date
April 2015
Construction started
February 2007
First registered
March 2007
Developer
Binary Development Limited
Community
Business Bay
Units
420
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا باينري من أمنيات
Project number
1174
Site inspections
7

Schedule

The register lists The Binary By Omniyat as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2008201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2015

100%+3.9 pts

  • The Binary By Omniyat construction site, inspection photo 1, 30 September 2015
  • The Binary By Omniyat construction site, inspection photo 2, 30 September 2015
  • The Binary By Omniyat construction site, inspection photo 3, 30 September 2015
  • The Binary By Omniyat construction site, inspection photo 4, 30 September 2015

14 May 2015

96%+16 pts

  • The Binary By Omniyat construction site, inspection photo 1, 14 May 2015
  • The Binary By Omniyat construction site, inspection photo 2, 14 May 2015
  • The Binary By Omniyat construction site, inspection photo 3, 14 May 2015
  • The Binary By Omniyat construction site, inspection photo 4, 14 May 2015

2 November 2014

80%+9.9 pts

  • The Binary By Omniyat construction site, inspection photo 1, 2 November 2014
  • The Binary By Omniyat construction site, inspection photo 2, 2 November 2014
  • The Binary By Omniyat construction site, inspection photo 3, 2 November 2014
  • The Binary By Omniyat construction site, inspection photo 4, 2 November 2014

28 June 2014

70%+7.7 pts

  • The Binary By Omniyat construction site, inspection photo 1, 28 June 2014
  • The Binary By Omniyat construction site, inspection photo 2, 28 June 2014
  • The Binary By Omniyat construction site, inspection photo 3, 28 June 2014
  • The Binary By Omniyat construction site, inspection photo 4, 28 June 2014

21 January 2014

62%+15 pts

  • The Binary By Omniyat construction site, inspection photo 1, 21 January 2014
  • The Binary By Omniyat construction site, inspection photo 2, 21 January 2014
  • The Binary By Omniyat construction site, inspection photo 3, 21 January 2014
  • The Binary By Omniyat construction site, inspection photo 4, 21 January 2014

16 July 2013

47%+25 pts

  • The Binary By Omniyat construction site, inspection photo 1, 16 July 2013
  • The Binary By Omniyat construction site, inspection photo 2, 16 July 2013
  • The Binary By Omniyat construction site, inspection photo 3, 16 July 2013
  • The Binary By Omniyat construction site, inspection photo 4, 16 July 2013

26 September 2012

23%

  • The Binary By Omniyat construction site, inspection photo 1, 26 September 2012
  • The Binary By Omniyat construction site, inspection photo 2, 26 September 2012
  • The Binary By Omniyat construction site, inspection photo 3, 26 September 2012
  • The Binary By Omniyat construction site, inspection photo 4, 26 September 2012

All 72 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in The Binary By Omniyat?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Binary By Omniyat handover date?
Construction of The Binary By Omniyat is recorded as complete, with a registered completion date of April 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Binary By Omniyat?
The Binary By Omniyat was 100% built at the site inspection on 30 September 2015. The site has been inspected 7 times since September 2012. The Land Department took 72 site photos at its inspections.
Is The Binary By Omniyat delayed?
The register lists construction as complete.
Who is building The Binary By Omniyat?
The registered developer is Binary Development Limited.
Which bank holds the escrow account for The Binary By Omniyat?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.