Sls Dubai construction progress

The register lists Sls Dubai in Business Bay as complete, with a registered completion date of January 2021. Its last site inspection on record was in January 2021. The developer is W O W Real Estate Development.

100%

Built, at the site inspection of 17 January 2021

Construction complete

Registered completion date
January 2021
Construction started
December 2015
First registered
April 2017
Developer
W O W Real Estate Development
Community
Business Bay
Units
1,159
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
اس ال اس دبي
Project number
1886
Site inspections
7

Schedule

The register lists Sls Dubai as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 January 2021

100%+9.0 pts

  • Sls Dubai construction site, inspection photo 1, 17 January 2021
  • Sls Dubai construction site, inspection photo 2, 17 January 2021
  • Sls Dubai construction site, inspection photo 3, 17 January 2021
  • Sls Dubai construction site, inspection photo 4, 17 January 2021

4 May 2020

91%+9.8 pts

  • Sls Dubai construction site, inspection photo 1, 4 May 2020
  • Sls Dubai construction site, inspection photo 2, 4 May 2020
  • Sls Dubai construction site, inspection photo 3, 4 May 2020
  • Sls Dubai construction site, inspection photo 4, 4 May 2020

13 January 2020

81%+8.0 pts

  • Sls Dubai construction site, inspection photo 1, 13 January 2020
  • Sls Dubai construction site, inspection photo 2, 13 January 2020
  • Sls Dubai construction site, inspection photo 3, 13 January 2020
  • Sls Dubai construction site, inspection photo 4, 13 January 2020

30 September 2019

73%+13 pts

  • Sls Dubai construction site, inspection photo 1, 30 September 2019
  • Sls Dubai construction site, inspection photo 2, 30 September 2019
  • Sls Dubai construction site, inspection photo 3, 30 September 2019
  • Sls Dubai construction site, inspection photo 4, 30 September 2019

9 April 2019

60%+9.1 pts

  • Sls Dubai construction site, inspection photo 1, 9 April 2019
  • Sls Dubai construction site, inspection photo 2, 9 April 2019
  • Sls Dubai construction site, inspection photo 3, 9 April 2019
  • Sls Dubai construction site, inspection photo 4, 9 April 2019

13 December 2018

51%+31 pts

  • Sls Dubai construction site, inspection photo 1, 13 December 2018
  • Sls Dubai construction site, inspection photo 2, 13 December 2018
  • Sls Dubai construction site, inspection photo 3, 13 December 2018
  • Sls Dubai construction site, inspection photo 4, 13 December 2018

23 October 2017

20%

  • Sls Dubai construction site, inspection photo 1, 23 October 2017
  • Sls Dubai construction site, inspection photo 2, 23 October 2017
  • Sls Dubai construction site, inspection photo 3, 23 October 2017
  • Sls Dubai construction site, inspection photo 4, 23 October 2017

All 80 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Sls Dubai?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sls Dubai handover date?
Construction of Sls Dubai is recorded as complete, with a registered completion date of January 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sls Dubai?
Sls Dubai was 100% built at the site inspection on 17 January 2021. The site has been inspected 7 times since October 2017. The Land Department took 80 site photos at its inspections.
Is Sls Dubai delayed?
The register lists construction as complete.
Who is building Sls Dubai?
The registered developer is W O W Real Estate Development.
Which bank holds the escrow account for Sls Dubai?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.