Sky Bay Hotel construction progress

The register lists Sky Bay Hotel in Business Bay as complete, with a registered completion date of March 2021. Its last site inspection on record was in July 2021. The developer is T F G Real Estate.

100%

Built, at the site inspection of 13 July 2021

Construction complete

Registered completion date
March 2021
Construction started
April 2016
First registered
June 2017
Developer
T F G Real Estate
Community
Business Bay
Units
711
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فندق سكاي باي
Project number
1909
Site inspections
14

Schedule

The register lists Sky Bay Hotel as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 July 2021

100%+2.8 pts

  • Sky Bay Hotel construction site, inspection photo 1, 13 July 2021
  • Sky Bay Hotel construction site, inspection photo 2, 13 July 2021
  • Sky Bay Hotel construction site, inspection photo 3, 13 July 2021
  • Sky Bay Hotel construction site, inspection photo 4, 13 July 2021

22 March 2021

97%+0.2 pts

  • Sky Bay Hotel construction site, inspection photo 1, 22 March 2021
  • Sky Bay Hotel construction site, inspection photo 2, 22 March 2021
  • Sky Bay Hotel construction site, inspection photo 3, 22 March 2021
  • Sky Bay Hotel construction site, inspection photo 4, 22 March 2021

29 November 2020

97%+2.2 pts

  • Sky Bay Hotel construction site, inspection photo 1, 29 November 2020
  • Sky Bay Hotel construction site, inspection photo 2, 29 November 2020
  • Sky Bay Hotel construction site, inspection photo 3, 29 November 2020
  • Sky Bay Hotel construction site, inspection photo 4, 29 November 2020

18 March 2020

95%+3.7 pts

  • Sky Bay Hotel construction site, inspection photo 1, 18 March 2020
  • Sky Bay Hotel construction site, inspection photo 2, 18 March 2020
  • Sky Bay Hotel construction site, inspection photo 3, 18 March 2020
  • Sky Bay Hotel construction site, inspection photo 4, 18 March 2020

27 November 2019

91%+1.1 pts

  • Sky Bay Hotel construction site, inspection photo 1, 27 November 2019
  • Sky Bay Hotel construction site, inspection photo 2, 27 November 2019
  • Sky Bay Hotel construction site, inspection photo 3, 27 November 2019
  • Sky Bay Hotel construction site, inspection photo 4, 27 November 2019

28 October 2019

90%+1.9 pts

  • Sky Bay Hotel construction site, inspection photo 1, 28 October 2019
  • Sky Bay Hotel construction site, inspection photo 2, 28 October 2019
  • Sky Bay Hotel construction site, inspection photo 3, 28 October 2019
  • Sky Bay Hotel construction site, inspection photo 4, 28 October 2019

18 June 2019

88%+5.1 pts

  • Sky Bay Hotel construction site, inspection photo 1, 18 June 2019
  • Sky Bay Hotel construction site, inspection photo 2, 18 June 2019
  • Sky Bay Hotel construction site, inspection photo 3, 18 June 2019
  • Sky Bay Hotel construction site, inspection photo 4, 18 June 2019

9 April 2019

83%+6.1 pts

  • Sky Bay Hotel construction site, inspection photo 1, 9 April 2019
  • Sky Bay Hotel construction site, inspection photo 2, 9 April 2019
  • Sky Bay Hotel construction site, inspection photo 3, 9 April 2019
  • Sky Bay Hotel construction site, inspection photo 4, 9 April 2019

4 February 2019

77%+3.3 pts

  • Sky Bay Hotel construction site, inspection photo 1, 4 February 2019
  • Sky Bay Hotel construction site, inspection photo 2, 4 February 2019
  • Sky Bay Hotel construction site, inspection photo 3, 4 February 2019
  • Sky Bay Hotel construction site, inspection photo 4, 4 February 2019

15 January 2019

74%+2.8 pts

  • Sky Bay Hotel construction site, inspection photo 1, 15 January 2019
  • Sky Bay Hotel construction site, inspection photo 2, 15 January 2019
  • Sky Bay Hotel construction site, inspection photo 3, 15 January 2019
  • Sky Bay Hotel construction site, inspection photo 4, 15 January 2019

All 160 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Sky Bay Hotel?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sky Bay Hotel handover date?
Construction of Sky Bay Hotel is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sky Bay Hotel?
Sky Bay Hotel was 100% built at the site inspection on 13 July 2021. The site has been inspected 14 times since November 2017. The Land Department took 160 site photos at its inspections.
Is Sky Bay Hotel delayed?
The register lists construction as complete.
Who is building Sky Bay Hotel?
The registered developer is T F G Real Estate.
Which bank holds the escrow account for Sky Bay Hotel?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.