Merano Tower construction progress

The register lists Merano Tower in Business Bay as complete, with a registered completion date of February 2020. Its last site inspection on record was in February 2020. The developer is Damac World Real Estate.

100%

Built, at the site inspection of 27 February 2020

Construction complete

Registered completion date
February 2020
Construction started
October 2015
First registered
August 2015
Developer
Damac World Real Estate
Community
Business Bay
Units
581
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج ميرانو
Project number
1680
Site inspections
10

Schedule

The register lists Merano Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 February 2020

100%+1.9 pts

  • Merano Tower construction site, inspection photo 1, 27 February 2020
  • Merano Tower construction site, inspection photo 2, 27 February 2020
  • Merano Tower construction site, inspection photo 3, 27 February 2020
  • Merano Tower construction site, inspection photo 4, 27 February 2020

2 January 2020

98%+18 pts

  • Merano Tower construction site, inspection photo 1, 2 January 2020
  • Merano Tower construction site, inspection photo 2, 2 January 2020
  • Merano Tower construction site, inspection photo 3, 2 January 2020
  • Merano Tower construction site, inspection photo 4, 2 January 2020

26 June 2019

80%+20 pts

  • Merano Tower construction site, inspection photo 1, 26 June 2019
  • Merano Tower construction site, inspection photo 2, 26 June 2019
  • Merano Tower construction site, inspection photo 3, 26 June 2019
  • Merano Tower construction site, inspection photo 4, 26 June 2019

22 January 2019

60%+17 pts

  • Merano Tower construction site, inspection photo 1, 22 January 2019
  • Merano Tower construction site, inspection photo 2, 22 January 2019
  • Merano Tower construction site, inspection photo 3, 22 January 2019
  • Merano Tower construction site, inspection photo 4, 22 January 2019

21 October 2018

43%+13 pts

  • Merano Tower construction site, inspection photo 1, 21 October 2018
  • Merano Tower construction site, inspection photo 2, 21 October 2018
  • Merano Tower construction site, inspection photo 3, 21 October 2018
  • Merano Tower construction site, inspection photo 4, 21 October 2018

7 June 2018

30%+10.0 pts

  • Merano Tower construction site, inspection photo 1, 7 June 2018
  • Merano Tower construction site, inspection photo 2, 7 June 2018
  • Merano Tower construction site, inspection photo 3, 7 June 2018
  • Merano Tower construction site, inspection photo 4, 7 June 2018

9 January 2018

20%+2.1 pts

  • Merano Tower construction site, inspection photo 1, 9 January 2018
  • Merano Tower construction site, inspection photo 2, 9 January 2018
  • Merano Tower construction site, inspection photo 3, 9 January 2018
  • Merano Tower construction site, inspection photo 4, 9 January 2018

16 August 2017

18%+0.2 pts

  • Merano Tower construction site, inspection photo 1, 16 August 2017
  • Merano Tower construction site, inspection photo 2, 16 August 2017
  • Merano Tower construction site, inspection photo 3, 16 August 2017
  • Merano Tower construction site, inspection photo 4, 16 August 2017

7 May 2017

18%+0.3 pts

  • Merano Tower construction site, inspection photo 1, 7 May 2017
  • Merano Tower construction site, inspection photo 2, 7 May 2017
  • Merano Tower construction site, inspection photo 3, 7 May 2017
  • Merano Tower construction site, inspection photo 4, 7 May 2017

8 December 2016

18%

  • Merano Tower construction site, inspection photo 1, 8 December 2016
  • Merano Tower construction site, inspection photo 2, 8 December 2016
  • Merano Tower construction site, inspection photo 3, 8 December 2016
  • Merano Tower construction site, inspection photo 4, 8 December 2016

All 91 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Merano Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Merano Tower handover date?
Construction of Merano Tower is recorded as complete, with a registered completion date of February 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Merano Tower?
Merano Tower was 100% built at the site inspection on 27 February 2020. The site has been inspected 10 times since December 2016. The Land Department took 91 site photos at its inspections.
Is Merano Tower delayed?
The register lists construction as complete.
Who is building Merano Tower?
The registered developer is Damac World Real Estate.
Which bank holds the escrow account for Merano Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.