Majestine construction progress

The register lists Majestine in Business Bay as complete, with a registered completion date of July 2018. Its last site inspection on record was in July 2018. The developer is Business Tower Investment.

100%

Built, at the site inspection of 25 July 2018

Construction complete

Registered completion date
July 2018
Construction started
August 2014
First registered
May 2014
Developer
Business Tower Investment
Community
Business Bay
Units
506
Escrow bank
Emirates NBD
Name in Arabic
ماجستين
Project number
1518
Site inspections
11

Schedule

The register lists Majestine as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 July 2018

100%+8.3 pts

  • Majestine construction site, inspection photo 1, 25 July 2018
  • Majestine construction site, inspection photo 2, 25 July 2018
  • Majestine construction site, inspection photo 3, 25 July 2018
  • Majestine construction site, inspection photo 4, 25 July 2018

12 March 2018

92%+10.0 pts

  • Majestine construction site, inspection photo 1, 12 March 2018
  • Majestine construction site, inspection photo 2, 12 March 2018
  • Majestine construction site, inspection photo 3, 12 March 2018
  • Majestine construction site, inspection photo 4, 12 March 2018

17 December 2017

82%+12 pts

  • Majestine construction site, inspection photo 1, 17 December 2017
  • Majestine construction site, inspection photo 2, 17 December 2017
  • Majestine construction site, inspection photo 3, 17 December 2017
  • Majestine construction site, inspection photo 4, 17 December 2017

27 August 2017

70%+10.0 pts

  • Majestine construction site, inspection photo 1, 27 August 2017
  • Majestine construction site, inspection photo 2, 27 August 2017
  • Majestine construction site, inspection photo 3, 27 August 2017
  • Majestine construction site, inspection photo 4, 27 August 2017

29 May 2017

60%+20 pts

  • Majestine construction site, inspection photo 1, 29 May 2017
  • Majestine construction site, inspection photo 2, 29 May 2017
  • Majestine construction site, inspection photo 3, 29 May 2017
  • Majestine construction site, inspection photo 4, 29 May 2017

4 January 2017

40%+20 pts

  • Majestine construction site, inspection photo 1, 4 January 2017
  • Majestine construction site, inspection photo 2, 4 January 2017
  • Majestine construction site, inspection photo 3, 4 January 2017
  • Majestine construction site, inspection photo 4, 4 January 2017

31 August 2016

20%+7.2 pts

  • Majestine construction site, inspection photo 1, 31 August 2016
  • Majestine construction site, inspection photo 2, 31 August 2016
  • Majestine construction site, inspection photo 3, 31 August 2016
  • Majestine construction site, inspection photo 4, 31 August 2016

21 April 2016

13%+5.8 pts

  • Majestine construction site, inspection photo 1, 21 April 2016
  • Majestine construction site, inspection photo 2, 21 April 2016
  • Majestine construction site, inspection photo 3, 21 April 2016
  • Majestine construction site, inspection photo 4, 21 April 2016

18 November 2015

7.0%+6.0 pts

  • Majestine construction site, inspection photo 1, 18 November 2015
  • Majestine construction site, inspection photo 2, 18 November 2015
  • Majestine construction site, inspection photo 3, 18 November 2015
  • Majestine construction site, inspection photo 4, 18 November 2015

7 April 2015

1.0%+0.6 pts

  • Majestine construction site, inspection photo 1, 7 April 2015
  • Majestine construction site, inspection photo 2, 7 April 2015
  • Majestine construction site, inspection photo 3, 7 April 2015
  • Majestine construction site, inspection photo 4, 7 April 2015

All 92 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Majestine?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Majestine handover date?
Construction of Majestine is recorded as complete, with a registered completion date of July 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Majestine?
Majestine was 100% built at the site inspection on 25 July 2018. The site has been inspected 11 times since December 2014. The Land Department took 92 site photos at its inspections.
Is Majestine delayed?
The register lists construction as complete.
Who is building Majestine?
The registered developer is Business Tower Investment.
Which bank holds the escrow account for Majestine?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.