Iris Bay construction progress

The register lists Iris Bay in Business Bay as complete, with a registered completion date of March 2015. Its last site inspection on record was in October 2015. The developer is Sheth Estate (International) Limited.

100%

Built, at the site inspection of 12 October 2015

Construction complete

Registered completion date
March 2015
Construction started
November 2007
First registered
November 2008
Developer
Sheth Estate (International) Limited
Community
Business Bay
Units
202
Escrow bank
Noor Bank
Name in Arabic
ايريس باي
Project number
127
Site inspections
3

Schedule

The register lists Iris Bay as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2008201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2015

100%+4.5 pts

  • Iris Bay construction site, inspection photo 1, 12 October 2015
  • Iris Bay construction site, inspection photo 2, 12 October 2015
  • Iris Bay construction site, inspection photo 3, 12 October 2015
  • Iris Bay construction site, inspection photo 4, 12 October 2015

22 September 2014

95%+0.0 pts

  • Iris Bay construction site, inspection photo 1, 22 September 2014
  • Iris Bay construction site, inspection photo 2, 22 September 2014
  • Iris Bay construction site, inspection photo 3, 22 September 2014
  • Iris Bay construction site, inspection photo 4, 22 September 2014

11 December 2012

95%

  • Iris Bay construction site, inspection photo 1, 11 December 2012
  • Iris Bay construction site, inspection photo 2, 11 December 2012
  • Iris Bay construction site, inspection photo 3, 11 December 2012
  • Iris Bay construction site, inspection photo 4, 11 December 2012

All 31 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Iris Bay?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Iris Bay handover date?
Construction of Iris Bay is recorded as complete, with a registered completion date of March 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Iris Bay?
Iris Bay was 100% built at the site inspection on 12 October 2015. The site has been inspected 3 times since December 2012. The Land Department took 31 site photos at its inspections.
Is Iris Bay delayed?
The register lists construction as complete.
Who is building Iris Bay?
The registered developer is Sheth Estate (International) Limited.
Which bank holds the escrow account for Iris Bay?
Noor Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.