Dolphin Tower construction progress
The register lists Dolphin Tower in Business Bay as complete, with a registered completion date of October 2020. Its last site inspection on record was in December 2020. The developer is T F G Real Estate.
100%
Built, at the site inspection of 8 December 2020
Construction complete
- Registered completion date
- October 2020
- Construction started
- July 2017
- First registered
- August 2018
- Developer
- T F G Real Estate
- Community
- Business Bay
- Units
- 340
- Escrow bank
- Emirates NBD
- Name in Arabic
- دولفين تاور
- Project number
- 2087
- Site inspections
- 9
Schedule
The register lists Dolphin Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
8 December 2020
100%+3.0 pts
12 August 2020
97%+6.7 pts
16 April 2020
90%+5.5 pts
19 December 2019
85%+11 pts
29 August 2019
73%+13 pts
22 April 2019
60%+10 pts
16 January 2019
50%+8.3 pts
20 November 2018
42%+12 pts
5 August 2018
30%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Dolphin Tower?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Dolphin Tower handover date?
- Construction of Dolphin Tower is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Dolphin Tower?
- Dolphin Tower was 100% built at the site inspection on 8 December 2020. The site has been inspected 9 times since August 2018. The Land Department took 89 site photos at its inspections.
- Is Dolphin Tower delayed?
- The register lists construction as complete.
- Who is building Dolphin Tower?
- The registered developer is T F G Real Estate.
- Which bank holds the escrow account for Dolphin Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)



.jpg&w=3840&q=75)