B2b Tower construction progress

The register lists B2b Tower in Business Bay as complete, with a registered completion date of April 2015. Its last site inspection on record was in July 2015. The developer is The Developer Properties.

100%

Built, at the site inspection of 29 July 2015

Construction complete

Registered completion date
April 2015
Construction started
September 2008
First registered
November 2008
Developer
The Developer Properties
Community
Business Bay
Units
263
Escrow bank
Dubai Islamic Bank
Name in Arabic
برج بي تو بي
Project number
19
Site inspections
3

Schedule

The register lists B2b Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 July 2015

97%+47 pts

  • B2b Tower construction site, inspection photo 1, 29 July 2015
  • B2b Tower construction site, inspection photo 2, 29 July 2015
  • B2b Tower construction site, inspection photo 3, 29 July 2015
  • B2b Tower construction site, inspection photo 4, 29 July 2015

12 May 2014

50%+18 pts

  • B2b Tower construction site, inspection photo 1, 12 May 2014
  • B2b Tower construction site, inspection photo 2, 12 May 2014
  • B2b Tower construction site, inspection photo 3, 12 May 2014
  • B2b Tower construction site, inspection photo 4, 12 May 2014

24 November 2012

31%

  • B2b Tower construction site, inspection photo 1, 24 November 2012
  • B2b Tower construction site, inspection photo 2, 24 November 2012
  • B2b Tower construction site, inspection photo 3, 24 November 2012

All 31 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in B2b Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the B2b Tower handover date?
Construction of B2b Tower is recorded as complete, with a registered completion date of April 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on B2b Tower?
B2b Tower was 100% built at the site inspection on 29 July 2015. The site has been inspected 3 times since November 2012. The Land Department took 31 site photos at its inspections.
Is B2b Tower delayed?
The register lists construction as complete.
Who is building B2b Tower?
The registered developer is The Developer Properties.
Which bank holds the escrow account for B2b Tower?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.