Avanti Tower construction progress

The register lists Avanti Tower in Business Bay as complete, with a registered completion date of December 2018. Its last site inspection on record was in December 2018. The developer is Damac Star Properties.

100%

Built, at the site inspection of 16 December 2018

Construction complete

Registered completion date
December 2018
Construction started
August 2014
First registered
May 2014
Developer
Damac Star Properties
Community
Business Bay
Units
161
Escrow bank
Emirates NBD
Name in Arabic
أفانتي تاور
Project number
1506
Site inspections
12

Schedule

The register lists Avanti Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 December 2018

100%+8.3 pts

  • Avanti Tower construction site, inspection photo 1, 16 December 2018
  • Avanti Tower construction site, inspection photo 2, 16 December 2018
  • Avanti Tower construction site, inspection photo 3, 16 December 2018
  • Avanti Tower construction site, inspection photo 4, 16 December 2018

1 July 2018

92%+11 pts

  • Avanti Tower construction site, inspection photo 1, 1 July 2018
  • Avanti Tower construction site, inspection photo 2, 1 July 2018
  • Avanti Tower construction site, inspection photo 3, 1 July 2018
  • Avanti Tower construction site, inspection photo 4, 1 July 2018

19 February 2018

81%+15 pts

  • Avanti Tower construction site, inspection photo 1, 19 February 2018
  • Avanti Tower construction site, inspection photo 2, 19 February 2018
  • Avanti Tower construction site, inspection photo 3, 19 February 2018
  • Avanti Tower construction site, inspection photo 4, 19 February 2018

23 October 2017

66%+14 pts

  • Avanti Tower construction site, inspection photo 1, 23 October 2017
  • Avanti Tower construction site, inspection photo 2, 23 October 2017
  • Avanti Tower construction site, inspection photo 3, 23 October 2017
  • Avanti Tower construction site, inspection photo 4, 23 October 2017

19 July 2017

53%+7.5 pts

  • Avanti Tower construction site, inspection photo 1, 19 July 2017
  • Avanti Tower construction site, inspection photo 2, 19 July 2017
  • Avanti Tower construction site, inspection photo 3, 19 July 2017
  • Avanti Tower construction site, inspection photo 4, 19 July 2017

3 April 2017

45%+7.3 pts

  • Avanti Tower construction site, inspection photo 1, 3 April 2017
  • Avanti Tower construction site, inspection photo 2, 3 April 2017
  • Avanti Tower construction site, inspection photo 3, 3 April 2017
  • Avanti Tower construction site, inspection photo 4, 3 April 2017

23 November 2016

38%+7.6 pts

  • Avanti Tower construction site, inspection photo 1, 23 November 2016
  • Avanti Tower construction site, inspection photo 2, 23 November 2016
  • Avanti Tower construction site, inspection photo 3, 23 November 2016
  • Avanti Tower construction site, inspection photo 4, 23 November 2016

31 August 2016

30%+10 pts

  • Avanti Tower construction site, inspection photo 1, 31 August 2016
  • Avanti Tower construction site, inspection photo 2, 31 August 2016
  • Avanti Tower construction site, inspection photo 3, 31 August 2016
  • Avanti Tower construction site, inspection photo 4, 31 August 2016

21 April 2016

20%+7.6 pts

  • Avanti Tower construction site, inspection photo 1, 21 April 2016
  • Avanti Tower construction site, inspection photo 2, 21 April 2016
  • Avanti Tower construction site, inspection photo 3, 21 April 2016
  • Avanti Tower construction site, inspection photo 4, 21 April 2016

18 November 2015

12%+2.2 pts

  • Avanti Tower construction site, inspection photo 1, 18 November 2015
  • Avanti Tower construction site, inspection photo 2, 18 November 2015
  • Avanti Tower construction site, inspection photo 3, 18 November 2015
  • Avanti Tower construction site, inspection photo 4, 18 November 2015

All 103 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Avanti Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Avanti Tower handover date?
Construction of Avanti Tower is recorded as complete, with a registered completion date of December 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Avanti Tower?
Avanti Tower was 100% built at the site inspection on 16 December 2018. The site has been inspected 12 times since December 2014. The Land Department took 103 site photos at its inspections.
Is Avanti Tower delayed?
The register lists construction as complete.
Who is building Avanti Tower?
The registered developer is Damac Star Properties.
Which bank holds the escrow account for Avanti Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.