The Waterway By Prestige One construction photos

27 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of The Waterway By Prestige One was built on the day of each visit.

17 August 202615% built

12 May 20268.4% built

20 January 20265.1% built

8 October 20251.4% built

20 June 20250.5% built

23 July 20240% built

Back to The Waterway By Prestige One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.