The Waterway By Prestige One construction photos
27 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of The Waterway By Prestige One was built on the day of each visit.
17 August 202615% built
12 May 20268.4% built
20 January 20265.1% built
8 October 20251.4% built
20 June 20250.5% built
23 July 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.