Vincitore Boulevard construction progress

The register lists Vincitore Boulevard in Arjan as complete, with a registered completion date of October 2020. Its last site inspection on record was in October 2020. The developer is Vincitore Real Estate Development.

100%

Built, at the site inspection of 8 October 2020

Construction complete

Registered completion date
October 2020
Construction started
April 2017
First registered
March 2017
Developer
Vincitore Real Estate Development
Community
Arjan
Units
248
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور بوليفارد
Project number
1879
Site inspections
6

Schedule

The register lists Vincitore Boulevard as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2020

100%+29 pts

  • Vincitore Boulevard construction site, inspection photo 1, 8 October 2020
  • Vincitore Boulevard construction site, inspection photo 2, 8 October 2020
  • Vincitore Boulevard construction site, inspection photo 3, 8 October 2020
  • Vincitore Boulevard construction site, inspection photo 4, 8 October 2020

9 September 2019

71%+16 pts

  • Vincitore Boulevard construction site, inspection photo 1, 9 September 2019
  • Vincitore Boulevard construction site, inspection photo 2, 9 September 2019
  • Vincitore Boulevard construction site, inspection photo 3, 9 September 2019
  • Vincitore Boulevard construction site, inspection photo 4, 9 September 2019

13 February 2019

55%+32 pts

  • Vincitore Boulevard construction site, inspection photo 1, 13 February 2019
  • Vincitore Boulevard construction site, inspection photo 2, 13 February 2019
  • Vincitore Boulevard construction site, inspection photo 3, 13 February 2019
  • Vincitore Boulevard construction site, inspection photo 4, 13 February 2019

29 July 2018

23%+13 pts

  • Vincitore Boulevard construction site, inspection photo 1, 29 July 2018
  • Vincitore Boulevard construction site, inspection photo 2, 29 July 2018
  • Vincitore Boulevard construction site, inspection photo 3, 29 July 2018
  • Vincitore Boulevard construction site, inspection photo 4, 29 July 2018

10 May 2018

11%+8.5 pts

  • Vincitore Boulevard construction site, inspection photo 1, 10 May 2018
  • Vincitore Boulevard construction site, inspection photo 2, 10 May 2018
  • Vincitore Boulevard construction site, inspection photo 3, 10 May 2018
  • Vincitore Boulevard construction site, inspection photo 4, 10 May 2018

11 October 2017

2.0%

  • Vincitore Boulevard construction site, inspection photo 1, 11 October 2017
  • Vincitore Boulevard construction site, inspection photo 2, 11 October 2017
  • Vincitore Boulevard construction site, inspection photo 3, 11 October 2017
  • Vincitore Boulevard construction site, inspection photo 4, 11 October 2017

All 60 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Vincitore Boulevard?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vincitore Boulevard handover date?
Construction of Vincitore Boulevard is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vincitore Boulevard?
Vincitore Boulevard was 100% built at the site inspection on 8 October 2020. The site has been inspected 6 times since October 2017. The Land Department took 60 site photos at its inspections.
Is Vincitore Boulevard delayed?
The register lists construction as complete.
Who is building Vincitore Boulevard?
The registered developer is Vincitore Real Estate Development.
Which bank holds the escrow account for Vincitore Boulevard?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.