Sunrise Legend construction progress

The register lists Sunrise Legend in Arjan as complete, with a registered completion date of August 2021. Its last site inspection on record was in August 2021. The developer is Sunrise Transcon Real Estate Development.

100%

Built, at the site inspection of 19 August 2021

Construction complete

Registered completion date
August 2021
Construction started
May 2018
First registered
September 2019
Developer
Sunrise Transcon Real Estate Development
Community
Arjan
Units
112
Escrow bank
Mashreq Bank
Name in Arabic
صنرايز ليجيند
Project number
2173
Site inspections
4

Schedule

The register lists Sunrise Legend as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2021

100%+1.7 pts

  • Sunrise Legend construction site, inspection photo 1, 19 August 2021
  • Sunrise Legend construction site, inspection photo 2, 19 August 2021
  • Sunrise Legend construction site, inspection photo 3, 19 August 2021
  • Sunrise Legend construction site, inspection photo 4, 19 August 2021

14 March 2021

98%+21 pts

  • Sunrise Legend construction site, inspection photo 1, 14 March 2021
  • Sunrise Legend construction site, inspection photo 2, 14 March 2021
  • Sunrise Legend construction site, inspection photo 3, 14 March 2021
  • Sunrise Legend construction site, inspection photo 4, 14 March 2021

23 December 2019

77%+23 pts

  • Sunrise Legend construction site, inspection photo 1, 23 December 2019
  • Sunrise Legend construction site, inspection photo 2, 23 December 2019
  • Sunrise Legend construction site, inspection photo 3, 23 December 2019
  • Sunrise Legend construction site, inspection photo 4, 23 December 2019

4 August 2019

54%

  • Sunrise Legend construction site, inspection photo 1, 4 August 2019
  • Sunrise Legend construction site, inspection photo 2, 4 August 2019
  • Sunrise Legend construction site, inspection photo 3, 4 August 2019
  • Sunrise Legend construction site, inspection photo 4, 4 August 2019

All 41 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Sunrise Legend?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sunrise Legend handover date?
Construction of Sunrise Legend is recorded as complete, with a registered completion date of August 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sunrise Legend?
Sunrise Legend was 100% built at the site inspection on 19 August 2021. The site has been inspected 4 times since August 2019. The Land Department took 41 site photos at its inspections.
Is Sunrise Legend delayed?
The register lists construction as complete.
Who is building Sunrise Legend?
The registered developer is Sunrise Transcon Real Estate Development.
Which bank holds the escrow account for Sunrise Legend?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.