Sunrise Legend construction progress
The register lists Sunrise Legend in Arjan as complete, with a registered completion date of August 2021. Its last site inspection on record was in August 2021. The developer is Sunrise Transcon Real Estate Development.
100%
Built, at the site inspection of 19 August 2021
Construction complete
- Registered completion date
- August 2021
- Construction started
- May 2018
- First registered
- September 2019
- Developer
- Sunrise Transcon Real Estate Development
- Community
- Arjan
- Units
- 112
- Escrow bank
- Mashreq Bank
- Name in Arabic
- صنرايز ليجيند
- Project number
- 2173
- Site inspections
- 4
Schedule
The register lists Sunrise Legend as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
19 August 2021
100%+1.7 pts
14 March 2021
98%+21 pts
23 December 2019
77%+23 pts
4 August 2019
54%
Context
Arjan has 23 projects under construction, 48% built on average.
Own a unit in Sunrise Legend?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Sunrise Legend handover date?
- Construction of Sunrise Legend is recorded as complete, with a registered completion date of August 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Sunrise Legend?
- Sunrise Legend was 100% built at the site inspection on 19 August 2021. The site has been inspected 4 times since August 2019. The Land Department took 41 site photos at its inspections.
- Is Sunrise Legend delayed?
- The register lists construction as complete.
- Who is building Sunrise Legend?
- The registered developer is Sunrise Transcon Real Estate Development.
- Which bank holds the escrow account for Sunrise Legend?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.