Siraj Tower construction progress

The register lists Siraj Tower in Arjan as complete, with a registered completion date of March 2016. Its last site inspection on record was in June 2016. The developer is Al Madar Investment.

100%

Built, at the site inspection of 9 June 2016

Construction complete

Registered completion date
March 2016
Construction started
October 2008
First registered
November 2008
Developer
Al Madar Investment
Community
Arjan
Units
374
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج سراج
Project number
181
Site inspections
7

Schedule

The register lists Siraj Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 June 2016

100%+8.3 pts

  • Siraj Tower construction site, inspection photo 1, 9 June 2016
  • Siraj Tower construction site, inspection photo 2, 9 June 2016
  • Siraj Tower construction site, inspection photo 3, 9 June 2016
  • Siraj Tower construction site, inspection photo 4, 9 June 2016

6 October 2015

92%+6.8 pts

  • Siraj Tower construction site, inspection photo 1, 6 October 2015
  • Siraj Tower construction site, inspection photo 2, 6 October 2015
  • Siraj Tower construction site, inspection photo 3, 6 October 2015
  • Siraj Tower construction site, inspection photo 4, 6 October 2015

17 May 2015

85%+11 pts

  • Siraj Tower construction site, inspection photo 1, 17 May 2015
  • Siraj Tower construction site, inspection photo 2, 17 May 2015
  • Siraj Tower construction site, inspection photo 3, 17 May 2015
  • Siraj Tower construction site, inspection photo 4, 17 May 2015

9 March 2015

74%+20 pts

  • Siraj Tower construction site, inspection photo 1, 9 March 2015
  • Siraj Tower construction site, inspection photo 2, 9 March 2015
  • Siraj Tower construction site, inspection photo 3, 9 March 2015
  • Siraj Tower construction site, inspection photo 4, 9 March 2015

18 October 2014

54%+24 pts

  • Siraj Tower construction site, inspection photo 1, 18 October 2014
  • Siraj Tower construction site, inspection photo 2, 18 October 2014
  • Siraj Tower construction site, inspection photo 3, 18 October 2014
  • Siraj Tower construction site, inspection photo 4, 18 October 2014

28 October 2013

30%+5.0 pts

  • Siraj Tower construction site, inspection photo 1, 28 October 2013
  • Siraj Tower construction site, inspection photo 2, 28 October 2013
  • Siraj Tower construction site, inspection photo 3, 28 October 2013
  • Siraj Tower construction site, inspection photo 4, 28 October 2013

4 June 2013

25%

  • Siraj Tower construction site, inspection photo 1, 4 June 2013
  • Siraj Tower construction site, inspection photo 2, 4 June 2013
  • Siraj Tower construction site, inspection photo 3, 4 June 2013
  • Siraj Tower construction site, inspection photo 4, 4 June 2013

All 67 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Siraj Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Siraj Tower handover date?
Construction of Siraj Tower is recorded as complete, with a registered completion date of March 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Siraj Tower?
Siraj Tower was 100% built at the site inspection on 9 June 2016. The site has been inspected 7 times since June 2013. The Land Department took 67 site photos at its inspections.
Is Siraj Tower delayed?
The register lists construction as complete.
Who is building Siraj Tower?
The registered developer is Al Madar Investment.
Which bank holds the escrow account for Siraj Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.