Avelon Boulevard construction progress

The register lists Avelon Boulevard in Arjan as complete, with a registered completion date of September 2025. Its last site inspection on record was in December 2025. The developer is Avelon Real Estate Development.

100%

Built, at the site inspection of 23 December 2025

Construction complete

Registered completion date
September 2025
Construction started
April 2024
First registered
June 2024
Developer
Avelon Real Estate Development
Community
Arjan
Units
135
Escrow bank
Emirates NBD
Name in Arabic
أفيلون بوليفارد
Project number
2984
Site inspections
5

Schedule

The register lists Avelon Boulevard as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 December 2025

100%+30 pts

  • Avelon Boulevard construction site, inspection photo 1, 23 December 2025
  • Avelon Boulevard construction site, inspection photo 2, 23 December 2025
  • Avelon Boulevard construction site, inspection photo 3, 23 December 2025
  • Avelon Boulevard construction site, inspection photo 4, 23 December 2025

23 April 2025

70%+32 pts

  • Avelon Boulevard construction site, inspection photo 1, 23 April 2025
  • Avelon Boulevard construction site, inspection photo 2, 23 April 2025
  • Avelon Boulevard construction site, inspection photo 3, 23 April 2025
  • Avelon Boulevard construction site, inspection photo 4, 23 April 2025

7 January 2025

38%+17 pts

  • Avelon Boulevard construction site, inspection photo 1, 7 January 2025
  • Avelon Boulevard construction site, inspection photo 2, 7 January 2025
  • Avelon Boulevard construction site, inspection photo 3, 7 January 2025
  • Avelon Boulevard construction site, inspection photo 4, 7 January 2025

26 September 2024

21%+21 pts

  • Avelon Boulevard construction site, inspection photo 1, 26 September 2024
  • Avelon Boulevard construction site, inspection photo 2, 26 September 2024
  • Avelon Boulevard construction site, inspection photo 3, 26 September 2024
  • Avelon Boulevard construction site, inspection photo 4, 26 September 2024

5 April 2024

0%

  • Avelon Boulevard construction site, inspection photo 1, 5 April 2024
  • Avelon Boulevard construction site, inspection photo 2, 5 April 2024
  • Avelon Boulevard construction site, inspection photo 3, 5 April 2024

All 35 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Avelon Real Estate Development has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Avelon Boulevard?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Avelon Boulevard handover date?
Construction of Avelon Boulevard is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Avelon Boulevard?
Avelon Boulevard was 100% built at the site inspection on 23 December 2025. The site has been inspected 5 times since April 2024. The Land Department took 35 site photos at its inspections.
Is Avelon Boulevard delayed?
The register lists construction as complete.
Who is building Avelon Boulevard?
The registered developer is Avelon Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Avelon Boulevard?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.