Ar II Camelia 2 construction progress
The register lists Ar II Camelia 2 in Arabian Ranches II - Dhalia as complete, with a registered completion date of November 2021. Its last site inspection on record was in November 2021. The developer is Emaar Development.
100%
Built, at the site inspection of 17 November 2021
Construction complete
- Registered completion date
- November 2021
- Construction started
- March 2019
- First registered
- November 2018
- Developer
- Emaar Development
- Community
- Arabian Ranches II - Dhalia
- Units
- 169
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كاميليا 2 Ii المرابع العربية
- Project number
- 2110
- Site inspections
- 10
Schedule
The register lists Ar II Camelia 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
17 November 2021
100%+7.2 pts
6 September 2021
93%+13 pts
25 May 2021
80%+7.1 pts
13 April 2021
73%+11 pts
16 December 2020
62%+8.9 pts
28 September 2020
53%+13 pts
9 June 2020
40%+18 pts
13 February 2020
23%+15 pts
31 October 2019
7.1%+6.8 pts
15 July 2019
0.3%
Context
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ar II Camelia 2?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Ar II Camelia 2 handover date?
- Construction of Ar II Camelia 2 is recorded as complete, with a registered completion date of November 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Ar II Camelia 2?
- Ar II Camelia 2 was 100% built at the site inspection on 17 November 2021. The site has been inspected 10 times since July 2019. The Land Department took 93 site photos at its inspections.
- Is Ar II Camelia 2 delayed?
- The register lists construction as complete.
- Who is building Ar II Camelia 2?
- The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
- Which bank holds the escrow account for Ar II Camelia 2?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.