Ar II Camelia 2 construction photos

93 photos from 10 site inspections, newest first. The percentage is how much of Ar II Camelia 2 was built on the day of each visit.

17 November 2021100% built

6 September 202193% built

25 May 202180% built

13 April 202173% built

16 December 202062% built

28 September 202053% built

9 June 202040% built

13 February 202023% built

31 October 20197.1% built

15 July 20190.3% built

Back to Ar II Camelia 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.