The Valley - Venera construction progress

The registered completion date for The Valley - Venera in Al Yufrah 1 is September 2028. At the last site inspection, in August 2026, it was 52% built. The developer is Emaar Development.

52%

Built, at the site inspection of 5 August 2026

On pace for its date

Registered completion date
September 2028
Finish at recent pace
September 2027
Construction started
September 2024
First registered
June 2024
Community
Al Yufrah 1
Units
696
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - فينيرا
Project number
3157
Site inspections
7

Schedule

Since August 2025 The Valley - Venera has added about 3.6 points a month. That puts 100% around September 2027, within three months of its registered completion date of September 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 August 2026

52%+11 pts

  • The Valley - Venera construction site, inspection photo 1, 5 August 2026
  • The Valley - Venera construction site, inspection photo 2, 5 August 2026
  • The Valley - Venera construction site, inspection photo 3, 5 August 2026
  • The Valley - Venera construction site, inspection photo 4, 5 August 2026

22 April 2026

40%+14 pts

  • The Valley - Venera construction site, inspection photo 1, 22 April 2026
  • The Valley - Venera construction site, inspection photo 2, 22 April 2026
  • The Valley - Venera construction site, inspection photo 3, 22 April 2026
  • The Valley - Venera construction site, inspection photo 4, 22 April 2026

11 December 2025

27%+16 pts

  • The Valley - Venera construction site, inspection photo 1, 11 December 2025
  • The Valley - Venera construction site, inspection photo 2, 11 December 2025
  • The Valley - Venera construction site, inspection photo 3, 11 December 2025
  • The Valley - Venera construction site, inspection photo 4, 11 December 2025

26 August 2025

11%+7.5 pts

  • The Valley - Venera construction site, inspection photo 1, 26 August 2025
  • The Valley - Venera construction site, inspection photo 2, 26 August 2025
  • The Valley - Venera construction site, inspection photo 3, 26 August 2025
  • The Valley - Venera construction site, inspection photo 4, 26 August 2025

30 May 2025

3.2%+2.0 pts

  • The Valley - Venera construction site, inspection photo 1, 30 May 2025
  • The Valley - Venera construction site, inspection photo 2, 30 May 2025
  • The Valley - Venera construction site, inspection photo 3, 30 May 2025
  • The Valley - Venera construction site, inspection photo 4, 30 May 2025

28 January 2025

1.2%+1.2 pts

  • The Valley - Venera construction site, inspection photo 1, 28 January 2025
  • The Valley - Venera construction site, inspection photo 2, 28 January 2025
  • The Valley - Venera construction site, inspection photo 3, 28 January 2025

24 June 2024

0%

  • The Valley - Venera construction site, inspection photo 1, 24 June 2024

All 44 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Venera?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Venera handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Venera?
The Valley - Venera was 52% built at the site inspection on 5 August 2026. The site has been inspected 7 times since June 2024. The Land Department took 44 site photos at its inspections.
Is The Valley - Venera delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2028.
Who is building The Valley - Venera?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Venera?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.