The Valley - Velora 2 construction progress

The Valley - Velora 2 in Al Yufrah 1 is 40% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for July 2028.

40%

Built, at the Land Department site inspection of 6 July 2026

On pace for its date

Completion date (Land Department)
July 2028
Finish at recent pace
March 2028
Construction started
November 2024
Registered with the Land Department
July 2024
Community
Al Yufrah 1
Units
312
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - فيلورا 2
Land Department project number
3161
Land Department site inspections
6

Schedule

Since July 2025 The Valley - Velora 2 has added about 3.0 points a month. That puts 100% around March 2028, within three months of its registered completion date of July 2028.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

40%+14 pts

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 6 July 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 2, 6 July 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 3, 6 July 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 4, 6 July 2026

3 March 2026

26%+9.6 pts

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 3 March 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 2, 3 March 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 3, 3 March 2026
  • The Valley - Velora 2 construction site, Land Department inspection photo 4, 3 March 2026

5 November 2025

17%+10 pts

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 5 November 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 2, 5 November 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 3, 5 November 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 4, 5 November 2025

24 July 2025

6.3%+4.7 pts

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 24 July 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 2, 24 July 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 3, 24 July 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 4, 24 July 2025

28 March 2025

1.5%+1.5 pts

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 28 March 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 2, 28 March 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 3, 28 March 2025
  • The Valley - Velora 2 construction site, Land Department inspection photo 4, 28 March 2025

21 June 2024

0%

  • The Valley - Velora 2 construction site, Land Department inspection photo 1, 21 June 2024

All 35 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average. The Valley - Velora 2 is ahead of that average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Velora 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Valley - Velora 2 be completed?
The completion date registered with the Dubai Land Department is July 2028. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Velora 2 is built?
40%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 6 times since June 2024.
Is The Valley - Velora 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of July 2028.
Who is building The Valley - Velora 2?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Velora 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.