The Valley - Velora construction progress

The Valley - Velora in Al Yufrah 1 is 50% built at the Land Department inspection of June 2026. Developer Emaar Development. Completion registered for August 2028.

50%

Built, at the Land Department site inspection of 9 June 2026

On pace for its date

Completion date (Land Department)
August 2028
Finish at recent pace
June 2027
Construction started
August 2024
Registered with the Land Department
June 2024
Community
Al Yufrah 1
Units
488
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - فيلورا
Land Department project number
3153
Land Department site inspections
6

Schedule

Since July 2025 The Valley - Velora has added about 4.0 points a month. That puts 100% around June 2027, within three months of its registered completion date of August 2028.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 June 2026

50%+10 pts

  • The Valley - Velora construction site, Land Department inspection photo 1, 9 June 2026
  • The Valley - Velora construction site, Land Department inspection photo 2, 9 June 2026
  • The Valley - Velora construction site, Land Department inspection photo 3, 9 June 2026
  • The Valley - Velora construction site, Land Department inspection photo 4, 9 June 2026

24 February 2026

40%+13 pts

  • The Valley - Velora construction site, Land Department inspection photo 1, 24 February 2026
  • The Valley - Velora construction site, Land Department inspection photo 2, 24 February 2026
  • The Valley - Velora construction site, Land Department inspection photo 3, 24 February 2026
  • The Valley - Velora construction site, Land Department inspection photo 4, 24 February 2026

6 November 2025

27%+19 pts

  • The Valley - Velora construction site, Land Department inspection photo 1, 6 November 2025
  • The Valley - Velora construction site, Land Department inspection photo 2, 6 November 2025
  • The Valley - Velora construction site, Land Department inspection photo 3, 6 November 2025
  • The Valley - Velora construction site, Land Department inspection photo 4, 6 November 2025

23 July 2025

8.3%+7.5 pts

  • The Valley - Velora construction site, Land Department inspection photo 1, 23 July 2025
  • The Valley - Velora construction site, Land Department inspection photo 2, 23 July 2025
  • The Valley - Velora construction site, Land Department inspection photo 3, 23 July 2025
  • The Valley - Velora construction site, Land Department inspection photo 4, 23 July 2025

14 April 2025

0.8%+0.8 pts

  • The Valley - Velora construction site, Land Department inspection photo 1, 14 April 2025
  • The Valley - Velora construction site, Land Department inspection photo 2, 14 April 2025
  • The Valley - Velora construction site, Land Department inspection photo 3, 14 April 2025
  • The Valley - Velora construction site, Land Department inspection photo 4, 14 April 2025

21 June 2024

0%

  • The Valley - Velora construction site, Land Department inspection photo 1, 21 June 2024

All 35 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Velora?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Valley - Velora be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Velora is built?
50%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since June 2024.
Is The Valley - Velora delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of August 2028.
Who is building The Valley - Velora?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Velora?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.