The Valley - Rivera construction progress

The registered completion date for The Valley - Rivera in Al Yufrah 1 is November 2028. At the last site inspection, in May 2026, it was 3.9% built. The developer is Emaar Development.

3.9%

Built, at the site inspection of 6 May 2026

Running behind its date

Registered completion date
November 2028
Finish at recent pace
September 2041
Construction started
October 2024
First registered
August 2024
Community
Al Yufrah 1
Units
378
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - ريفيرا
Project number
3174
Site inspections
3

Schedule

Between January 2026 and May 2026 the site added about 0.5 points a month. At that rate it would finish around September 2041, more than three months after its registered date of November 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 May 2026

3.9%+1.8 pts

  • The Valley - Rivera construction site, inspection photo 1, 6 May 2026
  • The Valley - Rivera construction site, inspection photo 2, 6 May 2026
  • The Valley - Rivera construction site, inspection photo 3, 6 May 2026
  • The Valley - Rivera construction site, inspection photo 4, 6 May 2026

20 January 2026

2.1%+2.1 pts

  • The Valley - Rivera construction site, inspection photo 1, 20 January 2026
  • The Valley - Rivera construction site, inspection photo 2, 20 January 2026
  • The Valley - Rivera construction site, inspection photo 3, 20 January 2026

3 July 2024

0%

  • The Valley - Rivera construction site, inspection photo 1, 3 July 2024

All 9 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Rivera?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Rivera handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Rivera?
The Valley - Rivera was 3.9% built at the site inspection on 6 May 2026. The site has been inspected 3 times since July 2024. The Land Department took 9 site photos at its inspections.
Is The Valley - Rivera delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
Who is building The Valley - Rivera?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Rivera?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.