The Valley - Orania construction progress

The register lists The Valley - Orania in Al Yufrah 1 as complete, with a registered completion date of December 2025. Its last site inspection on record was in July 2025. The developer is Emaar Development.

100%

Built, at the site inspection of 29 July 2025

Construction complete

Registered completion date
December 2025
Construction started
September 2022
First registered
June 2022
Community
Al Yufrah 1
Units
308
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ذا فالي - أورانيا
Project number
2409
Site inspections
6

Schedule

The register lists The Valley - Orania as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 July 2025

100%+4.9 pts

  • The Valley - Orania construction site, inspection photo 1, 29 July 2025
  • The Valley - Orania construction site, inspection photo 2, 29 July 2025
  • The Valley - Orania construction site, inspection photo 3, 29 July 2025
  • The Valley - Orania construction site, inspection photo 4, 29 July 2025

9 April 2025

95%+13 pts

  • The Valley - Orania construction site, inspection photo 1, 9 April 2025
  • The Valley - Orania construction site, inspection photo 2, 9 April 2025
  • The Valley - Orania construction site, inspection photo 3, 9 April 2025
  • The Valley - Orania construction site, inspection photo 4, 9 April 2025

15 December 2024

82%+14 pts

  • The Valley - Orania construction site, inspection photo 1, 15 December 2024
  • The Valley - Orania construction site, inspection photo 2, 15 December 2024
  • The Valley - Orania construction site, inspection photo 3, 15 December 2024
  • The Valley - Orania construction site, inspection photo 4, 15 December 2024

20 August 2024

68%+61 pts

  • The Valley - Orania construction site, inspection photo 1, 20 August 2024
  • The Valley - Orania construction site, inspection photo 2, 20 August 2024
  • The Valley - Orania construction site, inspection photo 3, 20 August 2024
  • The Valley - Orania construction site, inspection photo 4, 20 August 2024

21 September 2023

7.2%+5.5 pts

  • The Valley - Orania construction site, inspection photo 1, 21 September 2023
  • The Valley - Orania construction site, inspection photo 2, 21 September 2023
  • The Valley - Orania construction site, inspection photo 3, 21 September 2023
  • The Valley - Orania construction site, inspection photo 4, 21 September 2023

1 June 2023

1.7%

  • The Valley - Orania construction site, inspection photo 1, 1 June 2023
  • The Valley - Orania construction site, inspection photo 2, 1 June 2023
  • The Valley - Orania construction site, inspection photo 3, 1 June 2023

All 38 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Orania?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Valley - Orania handover date?
Construction of The Valley - Orania is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Valley - Orania?
The Valley - Orania was 100% built at the site inspection on 29 July 2025. The site has been inspected 6 times since June 2023. The Land Department took 38 site photos at its inspections.
Is The Valley - Orania delayed?
The register lists construction as complete.
Who is building The Valley - Orania?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Orania?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.