The Valley - Kaia construction progress
The registered completion date for The Valley - Kaia in Al Yufrah 1 is July 2028. At the last site inspection, in June 2026, it was 19% built. The developer is Emaar Development.
19%
Built, at the site inspection of 9 June 2026
Running behind its date
- Registered completion date
- July 2028
- Finish at recent pace
- September 2029
- Construction started
- February 2025
- First registered
- November 2024
- Developer
- Emaar Development
- Community
- Al Yufrah 1
- Units
- 156
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا فالي - كايا
- Project number
- 3405
- Site inspections
- 5
Schedule
Between October 2025 and June 2026 the site added about 2.1 points a month. At that rate it would finish around September 2029, more than three months after its registered date of July 2028.
Site inspections
9 June 2026
19%+12 pts
13 February 2026
7.1%+4.5 pts
10 October 2025
2.6%+2.3 pts
28 May 2025
0.3%+0.3 pts
14 November 2024
0%
Context
Al Yufrah 1 has 17 projects under construction, 40% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Valley - Kaia?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Valley - Kaia handover date?
- The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Valley - Kaia?
- The Valley - Kaia was 19% built at the site inspection on 9 June 2026. The site has been inspected 5 times since November 2024. The Land Department took 18 site photos at its inspections.
- Is The Valley - Kaia delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
- Who is building The Valley - Kaia?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Valley - Kaia?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Elwood EstatesNearby in Al Yufrah 1. 14%, Due June 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)