The Valley - Farm Grove 2 construction progress

The Valley - Farm Grove 2 in Al Yufrah 1 is 9.8% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for October 2028.

9.8%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
December 2034
Construction started
February 2025
Registered with the Land Department
December 2024
Community
Al Yufrah 1
Units
290
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - فارم جروف 2
Land Department project number
3431
Land Department site inspections
6

Schedule

Between September 2025 and July 2026 the site added about 0.9 points a month. At that rate it would finish around December 2034, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

9.8%+3.8 pts

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 6 July 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 6 July 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 3, 6 July 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 4, 6 July 2026

16 March 2026

6.0%+3.0 pts

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 16 March 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 16 March 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 3, 16 March 2026
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 4, 16 March 2026

16 December 2025

2.9%+1.5 pts

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 16 December 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 16 December 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 3, 16 December 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 4, 16 December 2025

23 September 2025

1.4%+1.1 pts

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 23 September 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 23 September 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 3, 23 September 2025

10 June 2025

0.3%+0.3 pts

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 10 June 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 10 June 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 3, 10 June 2025
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 4, 10 June 2025

27 November 2024

0%

  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 1, 27 November 2024
  • The Valley - Farm Grove 2 construction site, Land Department inspection photo 2, 27 November 2024

All 28 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Farm Grove 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Valley - Farm Grove 2 be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around December 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Farm Grove 2 is built?
9.8%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 6 times since November 2024.
Is The Valley - Farm Grove 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building The Valley - Farm Grove 2?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Farm Grove 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.