The Valley - Farm Grove construction progress
The registered completion date for The Valley - Farm Grove in Al Yufrah 1 is December 2028. At the last site inspection, in July 2026, it was 10% built. The developer is Emaar Development.
10%
Built, at the site inspection of 15 July 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- December 2034
- Construction started
- February 2025
- First registered
- December 2024
- Developer
- Emaar Development
- Community
- Al Yufrah 1
- Units
- 482
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ذا فالي - فارم جروف
- Project number
- 3430
- Site inspections
- 6
Schedule
Between September 2025 and July 2026 the site added about 0.9 points a month. At that rate it would finish around December 2034, more than three months after its registered date of December 2028.
Site inspections
15 July 2026
10%+2.6 pts
31 March 2026
7.4%+5.3 pts
30 December 2025
2.1%+0.7 pts
25 September 2025
1.4%+1.0 pts
10 June 2025
0.4%+0.4 pts
27 November 2024
0%
Context
Al Yufrah 1 has 17 projects under construction, 40% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Valley - Farm Grove?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Valley - Farm Grove handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Valley - Farm Grove?
- The Valley - Farm Grove was 10% built at the site inspection on 15 July 2026. The site has been inspected 6 times since November 2024. The Land Department took 25 site photos at its inspections.
- Is The Valley - Farm Grove delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building The Valley - Farm Grove?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Valley - Farm Grove?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Elwood EstatesNearby in Al Yufrah 1. 14%, Due June 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.