The Valley - Farm Grove construction progress

The registered completion date for The Valley - Farm Grove in Al Yufrah 1 is December 2028. At the last site inspection, in July 2026, it was 10% built. The developer is Emaar Development.

10%

Built, at the site inspection of 15 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
December 2034
Construction started
February 2025
First registered
December 2024
Community
Al Yufrah 1
Units
482
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - فارم جروف
Project number
3430
Site inspections
6

Schedule

Between September 2025 and July 2026 the site added about 0.9 points a month. At that rate it would finish around December 2034, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 July 2026

10%+2.6 pts

  • The Valley - Farm Grove construction site, inspection photo 1, 15 July 2026
  • The Valley - Farm Grove construction site, inspection photo 2, 15 July 2026
  • The Valley - Farm Grove construction site, inspection photo 3, 15 July 2026
  • The Valley - Farm Grove construction site, inspection photo 4, 15 July 2026

31 March 2026

7.4%+5.3 pts

  • The Valley - Farm Grove construction site, inspection photo 1, 31 March 2026
  • The Valley - Farm Grove construction site, inspection photo 2, 31 March 2026
  • The Valley - Farm Grove construction site, inspection photo 3, 31 March 2026
  • The Valley - Farm Grove construction site, inspection photo 4, 31 March 2026

30 December 2025

2.1%+0.7 pts

  • The Valley - Farm Grove construction site, inspection photo 1, 30 December 2025
  • The Valley - Farm Grove construction site, inspection photo 2, 30 December 2025
  • The Valley - Farm Grove construction site, inspection photo 3, 30 December 2025

25 September 2025

1.4%+1.0 pts

  • The Valley - Farm Grove construction site, inspection photo 1, 25 September 2025
  • The Valley - Farm Grove construction site, inspection photo 2, 25 September 2025
  • The Valley - Farm Grove construction site, inspection photo 3, 25 September 2025

10 June 2025

0.4%+0.4 pts

  • The Valley - Farm Grove construction site, inspection photo 1, 10 June 2025
  • The Valley - Farm Grove construction site, inspection photo 2, 10 June 2025
  • The Valley - Farm Grove construction site, inspection photo 3, 10 June 2025
  • The Valley - Farm Grove construction site, inspection photo 4, 10 June 2025

27 November 2024

0%

  • The Valley - Farm Grove construction site, inspection photo 1, 27 November 2024
  • The Valley - Farm Grove construction site, inspection photo 2, 27 November 2024

All 25 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Farm Grove?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Farm Grove handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Farm Grove?
The Valley - Farm Grove was 10% built at the site inspection on 15 July 2026. The site has been inspected 6 times since November 2024. The Land Department took 25 site photos at its inspections.
Is The Valley - Farm Grove delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building The Valley - Farm Grove?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Farm Grove?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.