The Valley - Elva construction progress

The registered completion date for The Valley - Elva in Al Yufrah 1 is October 2028. At the last site inspection, in November 2026, it was 50% built. The developer is Emaar Development.

50%

Built, at the site inspection of 11 November 2026

On pace for its date

Registered completion date
October 2028
Finish at recent pace
December 2027
Construction started
February 2025
First registered
December 2024
Community
Al Yufrah 1
Units
244
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - ايلفا
Project number
3462
Site inspections
6

Schedule

Since February 2026 The Valley - Elva has added about 3.9 points a month. That puts 100% around December 2027, within three months of its registered completion date of October 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 November 2026

50%+24 pts

  • The Valley - Elva construction site, inspection photo 1, 11 November 2026
  • The Valley - Elva construction site, inspection photo 2, 11 November 2026
  • The Valley - Elva construction site, inspection photo 3, 11 November 2026
  • The Valley - Elva construction site, inspection photo 4, 11 November 2026

9 June 2026

26%+11 pts

  • The Valley - Elva construction site, inspection photo 1, 9 June 2026
  • The Valley - Elva construction site, inspection photo 2, 9 June 2026
  • The Valley - Elva construction site, inspection photo 3, 9 June 2026
  • The Valley - Elva construction site, inspection photo 4, 9 June 2026

11 February 2026

15%+10 pts

  • The Valley - Elva construction site, inspection photo 1, 11 February 2026
  • The Valley - Elva construction site, inspection photo 2, 11 February 2026
  • The Valley - Elva construction site, inspection photo 3, 11 February 2026
  • The Valley - Elva construction site, inspection photo 4, 11 February 2026

10 September 2025

5.1%+3.7 pts

  • The Valley - Elva construction site, inspection photo 1, 10 September 2025
  • The Valley - Elva construction site, inspection photo 2, 10 September 2025
  • The Valley - Elva construction site, inspection photo 3, 10 September 2025
  • The Valley - Elva construction site, inspection photo 4, 10 September 2025

24 June 2025

1.5%+1.5 pts

  • The Valley - Elva construction site, inspection photo 1, 24 June 2025
  • The Valley - Elva construction site, inspection photo 2, 24 June 2025
  • The Valley - Elva construction site, inspection photo 3, 24 June 2025
  • The Valley - Elva construction site, inspection photo 4, 24 June 2025

20 December 2024

0%

  • The Valley - Elva construction site, inspection photo 1, 20 December 2024
  • The Valley - Elva construction site, inspection photo 2, 20 December 2024

All 39 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Elva?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Elva handover date?
The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Elva?
The Valley - Elva was 50% built at the site inspection on 11 November 2026. The site has been inspected 6 times since December 2024. The Land Department took 39 site photos at its inspections.
Is The Valley - Elva delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2028.
Who is building The Valley - Elva?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Elva?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.