The Valley - Avena construction progress

The Valley - Avena in Al Yufrah 1 is 24% built at the Land Department inspection of June 2026. Developer Emaar Development. Completion registered for June 2028.

24%

Built, at the Land Department site inspection of 16 June 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
April 2029
Construction started
June 2024
Registered with the Land Department
July 2024
Community
Al Yufrah 1
Units
322
Escrow bank
Emirates Islamic Bank
Name in Arabic
ذا فالي - آفينا
Land Department project number
3158
Land Department site inspections
5

Schedule

Between October 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around April 2029, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 June 2026

24%+4.6 pts

  • The Valley - Avena construction site, Land Department inspection photo 1, 16 June 2026
  • The Valley - Avena construction site, Land Department inspection photo 2, 16 June 2026
  • The Valley - Avena construction site, Land Department inspection photo 3, 16 June 2026
  • The Valley - Avena construction site, Land Department inspection photo 4, 16 June 2026

12 February 2026

20%+14 pts

  • The Valley - Avena construction site, Land Department inspection photo 1, 12 February 2026
  • The Valley - Avena construction site, Land Department inspection photo 2, 12 February 2026
  • The Valley - Avena construction site, Land Department inspection photo 3, 12 February 2026
  • The Valley - Avena construction site, Land Department inspection photo 4, 12 February 2026

10 October 2025

6.3%+4.1 pts

  • The Valley - Avena construction site, Land Department inspection photo 1, 10 October 2025
  • The Valley - Avena construction site, Land Department inspection photo 2, 10 October 2025
  • The Valley - Avena construction site, Land Department inspection photo 3, 10 October 2025
  • The Valley - Avena construction site, Land Department inspection photo 4, 10 October 2025

13 January 2025

2.1%+2.1 pts

  • The Valley - Avena construction site, Land Department inspection photo 1, 13 January 2025
  • The Valley - Avena construction site, Land Department inspection photo 2, 13 January 2025
  • The Valley - Avena construction site, Land Department inspection photo 3, 13 January 2025

24 June 2024

0%

  • The Valley - Avena construction site, Land Department inspection photo 1, 24 June 2024

All 23 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Avena?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Valley - Avena be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Avena is built?
24%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is The Valley - Avena delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building The Valley - Avena?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Avena?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.