Paradise Hills construction progress

Paradise Hills in Al Hebiah Fifth is 84% built at the Land Department inspection of September 2026. Developer Paradise Hills Development. Completion registered for December 2025.

84%

Built, at the Land Department site inspection of 10 September 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
December 2217
Construction started
October 2014
Registered with the Land Department
September 2014
Developer
Paradise Hills Development
Units
178
Escrow bank
Sharjah Islamic Bank
Name in Arabic
Paradise Hills
Land Department project number
1585
Land Department site inspections
22

Schedule

Paradise Hills was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around December 2217.

0%25%50%75%100%2015201820212024
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 September 2026

84%+0.0 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 10 September 2026
  • Paradise Hills construction site, Land Department inspection photo 2, 10 September 2026
  • Paradise Hills construction site, Land Department inspection photo 3, 10 September 2026
  • Paradise Hills construction site, Land Department inspection photo 4, 10 September 2026

5 August 2026

84%+0.0 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 5 August 2026
  • Paradise Hills construction site, Land Department inspection photo 2, 5 August 2026
  • Paradise Hills construction site, Land Department inspection photo 3, 5 August 2026
  • Paradise Hills construction site, Land Department inspection photo 4, 5 August 2026

3 February 2026

84%+0.5 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 3 February 2026
  • Paradise Hills construction site, Land Department inspection photo 2, 3 February 2026
  • Paradise Hills construction site, Land Department inspection photo 3, 3 February 2026
  • Paradise Hills construction site, Land Department inspection photo 4, 3 February 2026

7 July 2025

83%+3.4 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 7 July 2025
  • Paradise Hills construction site, Land Department inspection photo 2, 7 July 2025
  • Paradise Hills construction site, Land Department inspection photo 3, 7 July 2025
  • Paradise Hills construction site, Land Department inspection photo 4, 7 July 2025

9 October 2024

80%+20 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 9 October 2024
  • Paradise Hills construction site, Land Department inspection photo 2, 9 October 2024
  • Paradise Hills construction site, Land Department inspection photo 3, 9 October 2024
  • Paradise Hills construction site, Land Department inspection photo 4, 9 October 2024

15 February 2024

60%+9.9 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 15 February 2024
  • Paradise Hills construction site, Land Department inspection photo 2, 15 February 2024
  • Paradise Hills construction site, Land Department inspection photo 3, 15 February 2024
  • Paradise Hills construction site, Land Department inspection photo 4, 15 February 2024

3 August 2023

50%+5.0 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 3 August 2023
  • Paradise Hills construction site, Land Department inspection photo 2, 3 August 2023
  • Paradise Hills construction site, Land Department inspection photo 3, 3 August 2023
  • Paradise Hills construction site, Land Department inspection photo 4, 3 August 2023

29 December 2022

45%+4.0 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 29 December 2022
  • Paradise Hills construction site, Land Department inspection photo 2, 29 December 2022
  • Paradise Hills construction site, Land Department inspection photo 3, 29 December 2022
  • Paradise Hills construction site, Land Department inspection photo 4, 29 December 2022

20 October 2022

41%+2.0 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 20 October 2022
  • Paradise Hills construction site, Land Department inspection photo 2, 20 October 2022
  • Paradise Hills construction site, Land Department inspection photo 3, 20 October 2022
  • Paradise Hills construction site, Land Department inspection photo 4, 20 October 2022

30 May 2022

39%+0.8 pts

  • Paradise Hills construction site, Land Department inspection photo 1, 30 May 2022
  • Paradise Hills construction site, Land Department inspection photo 2, 30 May 2022
  • Paradise Hills construction site, Land Department inspection photo 3, 30 May 2022
  • Paradise Hills construction site, Land Department inspection photo 4, 30 May 2022

All 177 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 48% built on average.

Own a unit in Paradise Hills?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Paradise Hills be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around December 2217. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Paradise Hills is built?
84%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 22 times since May 2015.
Is Paradise Hills delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Paradise Hills?
The registered developer is Paradise Hills Development.
Which bank holds the escrow account for Paradise Hills?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.