Paradise Hills construction progress
Paradise Hills in Al Hebiah Fifth was registered to complete in December 2025 and is still under construction. At the last site inspection, in September 2026, it was 84% built. The developer is Paradise Hills Development.
84%
Built, at the site inspection of 10 September 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- December 2217
- Construction started
- October 2014
- First registered
- September 2014
- Developer
- Paradise Hills Development
- Community
- Al Hebiah Fifth
- Units
- 178
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- Paradise Hills
- Project number
- 1585
- Site inspections
- 22
Schedule
Paradise Hills was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around December 2217.
Site inspections
10 September 2026
84%+0.0 pts
5 August 2026
84%+0.0 pts
3 February 2026
84%+0.5 pts
7 July 2025
83%+3.4 pts
9 October 2024
80%+20 pts
15 February 2024
60%+9.9 pts
3 August 2023
50%+5.0 pts
29 December 2022
45%+4.0 pts
20 October 2022
41%+2.0 pts
30 May 2022
39%+0.8 pts
Context
Al Hebiah Fifth has 20 projects under construction, 49% built on average.
Own a unit in Paradise Hills?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Paradise Hills handover date?
- The registered completion date was December 2025, and the register still lists Paradise Hills as under construction. At the pace of its recent inspections the site would reach 100% around December 2217. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Paradise Hills?
- Paradise Hills was 84% built at the site inspection on 10 September 2026. The site has been inspected 22 times since May 2015. The Land Department took 177 site photos at its inspections.
- Is Paradise Hills delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Paradise Hills?
- The registered developer is Paradise Hills Development.
- Which bank holds the escrow account for Paradise Hills?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - IbizaNearby in Al Hebiah Fifth. 79%, Due December 2025, passed.
- Damac Lagoons - MykonosNearby in Al Hebiah Fifth. 81%, Due December 2025, passed.
- Damac Lagoons - Monte CarloNearby in Al Hebiah Fifth. 86%, Due December 2025, passed.
- Damac Lagoons - MarbellaNearby in Al Hebiah Fifth. 87%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.