Damac Lagoons - Malta (1) construction progress
The register lists Damac Lagoons - Malta (1) in Al Hebiah Fifth as complete, with a registered completion date of September 2025. Its last site inspection on record was in June 2026. The developer is Island Oasis Properties.
100%
Built, at the site inspection of 6 June 2026
Construction complete
- Registered completion date
- September 2025
- Construction started
- August 2022
- First registered
- May 2022
- Developer
- Island Oasis Properties
- Community
- Al Hebiah Fifth
- Units
- 760
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- داماك لاجونز - مالتا (1)
- Project number
- 2400
- Site inspections
- 9
Schedule
The register lists Damac Lagoons - Malta (1) as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
6 June 2026
100%+5.1 pts
10 November 2025
95%+1.8 pts
3 June 2025
93%+15 pts
4 February 2025
78%+16 pts
16 September 2024
62%+25 pts
17 April 2024
37%+32 pts
22 August 2023
4.3%+3.7 pts
5 May 2023
0.7%+0.6 pts
21 December 2022
0.1%
Context
Al Hebiah Fifth has 20 projects under construction, 49% built on average.
Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.
Own a unit in Damac Lagoons - Malta (1)?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Damac Lagoons - Malta (1) handover date?
- Construction of Damac Lagoons - Malta (1) is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Damac Lagoons - Malta (1)?
- Damac Lagoons - Malta (1) was 100% built at the site inspection on 6 June 2026. The site has been inspected 9 times since December 2022. The Land Department took 62 site photos at its inspections.
- Is Damac Lagoons - Malta (1) delayed?
- The register lists construction as complete.
- Who is building Damac Lagoons - Malta (1)?
- The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Lagoons - Malta (1)?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - Nice 1Also by Island Oasis Properties. 94%, Due July 2025, passed.
- Damac Lagoons - Nice 2Also by Island Oasis Properties. 84%, Due July 2025, passed.
- Damac Lagoons - Venice (1)Also by Island Oasis Properties. 74%, Due September 2025, passed.
- Damac Lagoons - IbizaAlso by Island Oasis Properties. 79%, Due December 2025, passed.
- Paradise HillsNearby in Al Hebiah Fifth. 84%, Due December 2025, passed.
- Reportage HillsNearby in Al Hebiah Fifth. 0.4%, Due June 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)