Damac Lagoons - Malta (1) construction photos

62 photos from 9 site inspections, newest first. The percentage is how much of Damac Lagoons - Malta (1) was built on the day of each visit.

6 June 2026100% built

10 November 202595% built

3 June 202593% built

4 February 202578% built

16 September 202462% built

17 April 202437% built

22 August 20234.3% built

5 May 20230.7% built

21 December 20220.1% built

Back to Damac Lagoons - Malta (1) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.